File #: 22-2953    Version: 1 Name:
Type: Consent Agenda Status: Agenda Ready
File created: 5/20/2022 In control: City Commission Regular Meeting
On agenda: 6/28/2022 Final action: 6/28/2022
Title: Discussion and Possible Action Regarding the Approval of the Award of Request for Bid (RFB) No. 2022-23 for Construction of the Myakkahatchee Creek Greenway Trail to Gale Construction Company of Illinois for the Amount of $1,908,812.07 and Contingency in the Amount of $133,000 for the Total Amount of $2,014,812.07.
Attachments: 1. Contract, 2. Notice of Intent to Award, 3. Award Recommendation, 4. Comparison Bid Tabulation, 5. Bid Submittal, 6. Bid Document with Addenda, 7. Florida Division of Corporations Documents
TO: Honorable Mayor & Members of the North Port Commission

FROM: A. Jerome Fletcher II, ICMA-CM, MPA, City Manager
TITLE: Approve the Award of Request for Bid (RFB) No. 2022-23 for Construction of the Myakkahatchee Creek Greenway Trail to Gale Construction Company of Illinois for the Amount of $1,908,812.07 and Contingency in the Amount of $133,000 for the Total Amount of $2,014,812.07.


Recommended Action

Approve the Award of Request for Bid (RFB) No. 2022-23 for the construction of the Myakkahatchee Creek Greenway Trail Project to Gale Construction Company of Illinois for the amount of $1,908,812.07 and contingency in the amount of $133,000 for the total amount of $2,014,812.07.

Background Information

The Myakkahatchee Creek Greenway Trail Project is the first phase of the Myakkahatchee Creek Greenway Master Plan that was approved in 2007. This one-mile trail is located adjacent to the Myakkahatchee Creek between Appomattox Boulevard and West Price Boulevard and supports the linear park concept.

RFB No. 2022-23 for construction of the Myakkahatchee Creek Greenway Trail Project was advertised on February 18, 2022, and closed on March 25, 2022, with four bids received. These bids ranged from $1,908,812 to $2,760,551 for the base bid. All four bids submitted exceeded the available project budget of $1,722,412 and expenditures to date of $69,974. The low bidder, Gale Construction Company of Illinois, who has been deemed responsive, is $186,400 in excess of the total project budget. Staff has requested a budget amendment in the amount of $319,400 via Resolution 2022-R-31 to fully fund this project through Park Impact Fees. This amount includes a 7% contingency. It is estimated that construction will take 18 months from the City's construction Notice to Proceed. To facilitate moving this project forward, Gale Construction Company has agreed to extend the bid validity period from 90 days to 120 days.

The first reading of Resolution 2022-R-31 was heard at t...

Click here for full text