File #: 17-1474    Version: 1 Name:
Type: Consent Agenda Status: Passed
File created: 11/6/2017 In control: City Commission Regular Meeting
On agenda: 11/28/2017 Final action: 11/28/2017
Title: Award for RFB No. 2018-14, Pine Park Flexi-Pave Walking Paths to Peak Power Services, Inc. in the amount of $98,608.80 plus an estimated construction contingency of $10,000 for estimated budgeted construction cost of $108,608.80.
Sponsors: Cheryl Greiner
Attachments: 1. Notice of Intent to Award, 2. RFB 2018-14 Award Recommendation Memo, 3. RFB 2018-14 Comparison Sheet, 4. RFB 2018-14 with Addendum, 5. Peak Power Services Inc Submittal, 6. Florida Division of Corporations document
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
TO: Honorable Mayor & Members of the North Port Commission

FROM: Peter D. Lear, CPA, CGMA, City Manager

TITLE: Award for RFB No. 2018-14, Pine Park Flexi-Pave Walking Paths to Peak Power Services, Inc. in the amount of $98,608.80 plus a contingency of $10,000 for a total of $108,608.80. The project was adopted in the fiscal year 2017 budget.


Recommended Action

Approve award for RFB No. 2018-14, Pine Park Flexi-Pave Walking Paths to Peak Power Services, Inc. in the amount of $98,608.80 plus a contingency of $10,000 for a total of $108,608.80. The project was adopted in the fiscal year 2017 budget.


Background Information

The General Services Department is requesting approval from Commission to award RFB No. 2018-14 to install the Flexi-Pave walking paths at Pine Park. This is the first City Park facility that will utilize the Flexi-Pave product which is an environmentally-friendly, porous, clean and flexible surface that utilizes recycled tires and other materials. In addition to these features, Flexi-Pave is ADA compliant and a low-maintenance material. This product has been successfully implemented in other parks across the country including Yellowstone National Park. The Pine Park project will utilize 3,540 square feet of the Flexi-Pave product which equates to just over 1,000 recycled tires.

The Pine Park Flexi-Pave Walking Paths project was advertised on October 3, 2017. A Non-Mandatory pre-bid meeting was held on October 11, 2017. Three (3) bids were received, opened and read on November 1, 2017 at 2:00pm. Peak Power Services, Inc, was the lowest responsive and responsible bidder with a bid of $98,608.80.

Based on successful reference checks, the General Services Department recommends award to Peak Power Services, Inc. Upon a 14-day notice, awarded Contractor will be able to begin construction. Staff anticipates construction will take approximately ten weeks. In conjunction with the walking path, some minor parking lot updates and fence impro...