TO: Honorable Mayor & Members of the North Port Commission
FROM: A. Jerome Fletcher II, ICMA-CM, MPA, City Manager
TITLE: Approve Contract No. 2025-43 - Inflow and Infiltration Mitigation Community Development Block Grant-Mitigation By and Between the City of North Port, Florida, and Inliner Solutions, LLC, in the Amount of $368,132.00 With a Contingency of $36,813.00 for a Total Amount of $404,945.00, for Pipe Lining of Identified Sections of the Utilities Wastewater Collection System.
Recommended Action
Option 1: Approve Contract No. 2025-43 - Inflow and Infiltration Mitigation Community Development Block Grant-Mitigation by and between the City of North Port, Florida and Inliner Solutions, LLC, in the amount of $368,132.00 with a contingency of $36,813.00 for a total amount of $404,945.00, for pipe lining of identified sections of the utilities wastewater collection system.
Additional Commission Options
Option 1: Approve Contract No. 2025-43 - Inflow and Infiltration Mitigation Community Development Block Grant-Mitigation by and between the City of North Port, Florida and Inliner Solutions, LLC, in the amount of $368,132.00 with a contingency of $36,813.00 for a total amount of $404,945.00, for pipe lining of identified sections of the Utilities wastewater collection system.
* Pros: Proactively repair/line gravity mains at risk of failure while ensuring compliance with the draft Consent Order for Inflow & Infiltration (I&I) rehabilitation. Grant funded with no match required.
* Cons: Utility funds and staff time will be allocated for this project, which could be used for other projects.
Option 2: Deny Contract No. 2025-43 - Inflow and Infiltration Mitigation Community Development Block Grant-Mitigation by and between the City of North Port, Florida, and Inliner Solutions, LLC, in the amount of $368,132.00 with a contingency of $36,813.00 for a total amount of $404,945.00, for pipe lining of identified sections of the utilities wastewater collection s...