Legislation Details

File #: 26-0607    Version: 1 Name:
Type: Consent Agenda Status: Agenda Ready
File created: 3/30/2026 In control: City Commission Regular Meeting
On agenda: 5/19/2026 Final action:
Title: Approve Work Assignment No. 2023-40.003 IT2-2026 - I&I - CIPP - Freemont Street and LS-21 with Insituform Technologies, LLC for Cured in Place Pipe Lining of Areas Identified of High Inflow & Infiltration Around Freemont Street and Lift Station 21 in the Amount of $896,857.35
Attachments: 1. Work Assignment No. 2023-40.003 IT2-2026, 2. Assignment, Assumption, and First Amendment to Contract No. 2023-40.003, 3. Contract No. 2023-40.003, 4. Request for Bid 2023-40 Award Recommendation, 5. Request for Bid 2023-40, 6. Florida Division of Corporations Documents
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
TO: Honorable Mayor & Members of the North Port Commission

FROM: A. Jerome Fletcher II, ICMA-CM, MPA, City Manager

TITLE: Approve Work Assignment No. 2023-40.003 IT2-2026 - Inflow & Infiltration Rehabilitation - CIPP- Freemont Street and LS-21 with Insituform Technologies, LLC for Cured in Place Pile Lining of Areas Identified of High Inflow and Infiltration Around Freemont Street and Lift Station 21 in the Amount of $896,857.35


Recommended Action

Option 1: Approve Work Assignment No. 2023-40.003 IT2-2026 - Inflow & Infiltration Rehabilitation - CIPP - Freemont Street and LS-21 with Insituform Technologies, LLC for cured in place pile lining of areas identified of high inflow & infiltration around Freemont Street and Lift Station 21 in the Amount of $896,857.35.

Additional Commission Options

Option 1: Approve Work Assignment No. 2023-40.003 IT2-2026 - Inflow & Infiltration Rehabilitation - CIPP - Freemont Street and LS-21 with Insituform Technologies, LLC for cured in place pile lining of areas identified of high inflow & infiltration around Freemont Street and Lift Station 21 in the Amount of $896,857.35.

* Pros: Proactively line gravity mains at risk of failure while ensuring compliance with the draft Consent Order for I&I rehabilitation.
* Cons: Commits utility funds to this project, which could be used on other projects.

Option 2: Deny Work Assignment No. 2023-40.003 IT2-2026 - Inflow & Infiltration Rehabilitation - CIPP - Freemont Street and LS-21 with Insituform Technologies, LLC for cured in place pile lining of areas identified of high inflow & infiltration around Freemont Street and Lift Station 21 in the Amount of $896,857.35.

* Pros: Preserves utility funds for allocation to other utility projects.
* Cons: Denial of the Work Assignment would result in increased risk of gravity main failure and would limit the City's ability to address Inflow and Infiltration in this area.

Background Information

Inflow and infiltration (I&I) are extraneous ...

Click here for full text