File #: 25-2205    Version: 1 Name:
Type: Consent Agenda Status: Agenda Ready
File created: 4/15/2025 In control: City Commission Regular Meeting
On agenda: 5/13/2025 Final action:
Title: Approve the Fifteenth Amendment to Construction Manager at Risk Contract No. 2023-17.002 for Construction Services Contract, Phase II With Halfacre Construction Company in the Amount of $44,017.42, for Hurricane Ian Repairs at Highland Ridge Park.
Attachments: 1. Fifteenth Amendment to Contract, 2. Seventh Amendment to Contract, 3. Contract, 4. Work Assignment 2024-08FM, 5. Florida Division of Corporations Document
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
TO: Honorable Mayor & Members of the North Port Commission

FROM: A. Jerome Fletcher II, ICMA-CM, MPA, City Manager

TITLE: Approve the Fifteenth Amendment to Construction Manager at Risk Contract No. 2023-17.002 for Construction Services Contract, Phase II With Halfacre Construction Company in the Amount of $44,017.42, for Hurricane Ian Repairs at Highland Ridge Park.


Recommended Action

Approve the Fifteenth Amendment to Construction Manager at Risk Contract No. 2023-17.002 for Construction Services Contract, Phase II with Halfacre Construction Company in the amount of $44,017.42, for Hurricane Ian Repairs at Highland Ridge Park.

Background Information

As a result of impacts from Hurricane Ian, Highland Ridge Park suffered damage to the playground shade structure supports, as outlined in the Halliwell Construction Services and Rostan Damage Assessment Report. While initial repairs were underway at Highland Ridge Park, Halfacre Construction Company and City staff discovered that the playground shade structure had structural damage that exceeded the scope of repairs covered by the Guaranteed Maximum Price (GMP) allowance awarded as part of the Seventh Amendment to Contract No. 2023-17.002. As a result, the structure needs to be fully replaced to restore the park to its pre-hurricane condition.

In consultation with City Administration, the use of the Construction Manager at Risk (CMaR) Continuing Services Contract has been identified as the most expedient path to complete this project. The following describes the CMaR process specific to this project:

> September 24, 2024: Seventh Amendment to Contract No. 2023-17.002 encompassing Work Assignment No. 2024-08FM was issued to Halfacre Construction Company for the Pre-Construction Phase (Phase I) services. During this phase, the Contractor evaluated the work required, obtained quotes from applicable contractors, and developed the GMP.

> February 7, 2025: Halfacre Construction Company submitted a GMP proposal...

Click here for full text