Title: An Ordinance of the City of North Port, Florida, Amending the Non-District Budget for Fiscal Year 2024-2025 for Hurricane Ian and Hurricane Milton Costs and Payments From Park Impact Fees From the West Villages Developer Agreement (Post Annexation) in the Amount of $823,398; Providing for Findings; Providing for Posting; Providing for Conflicts; Providing for Severability; and Providing an Effective Date.
Attachments: 1. Ordinance No. 2025-08, 2. Fund Balance Report
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
TO: Honorable Mayor & Members of the North Port Commission

FROM: A. Jerome Fletcher II, ICMA-CM, MPA, City Manager

TITLE: An Ordinance of the City of North Port, Florida, Amending the Non-District Budget for Fiscal Year 2024-2025 for Hurricane Ian and Hurricane Milton Costs and Payments from Park Impact Fees from the West Villages Developer Agreement (Post Annexation) in the Amount of $823,398; Providing for Findings; Providing for Posting; Providing for Conflicts; Providing for Severability; and Providing an Effective Date.


Recommended Action

Approve Ordinance No. 2025-08 and move to second reading on March 11, 2025.

Background Information

General Fund

As Halfacre Construction mobilized to begin the Hurricane Ian repairs at LaBrea Park damages to the steel support system were identified which were not originally indicated on the damage assessment reports prepared by Rostan and Willdan. The damages are beyond repairable, and in order to replace the fabric shade cover the main support structure must be replaced. The initial Guaranteed Maximum Price (GMP) included the cost for the replacement fabric shade cover, with the intent to reuse the existing structure. With these additional damages identified, the Parks & Recreation Department is requesting a budget amendment in the amount of $30,459 to replace the damaged support structure. Staff is preparing a change order to Agreement 2023-17.002, Amendment #5, with Halfacre Construction.
After conversations with the Risk Division and Grants Division staff, no additional insurance or Federal Emergency Management Agency (FEMA) recoveries are anticipated for this repair. The funding for this request will come from General Fund balance.

Parks Impact Fees Fund (152)

The amendment and restatement of the West Villages Developer Agreement (Post Annexation) became effective on November 12, 2024. Within this Agreement, section 4.1(f) identified the City's responsibility to pay the developer for costs associated with th...