File #: 24-0965    Version: 1 Name:
Type: Consent Agenda Status: Agenda Ready
File created: 6/26/2024 In control: City Commission Regular Meeting
On agenda: 7/23/2024 Final action:
Title: Approve the Fifth Amendment to Construction Manager at Risk Contract No. 2023-17.004 for Construction Services Contract, Phase II With Jon F. Swift, Inc. in the Amount of $92,757, for Hurricane Ian Repairs at the East Kayak Launch at Water Control Structure 106.
Attachments: 1. Fifth Amendment to Contract, 2. Contract, 3. Work Assignment 2024-34FM, 4. Florida Division of Corporations Document
TO: Honorable Mayor & Members of the North Port Commission

FROM: A. Jerome Fletcher II, ICMA-CM, MPA, City Manager

TITLE: Approve Fifth Amendment to Construction Manager at Risk Contract No. 2023-17.004 for Construction Services Contract, Phase II With Jon F. Swift, Inc. in the Amount of $92,757, for Hurricane Ian Repairs at the East Kayak Launch at Water Control Structure 106.


Recommended Action

Approve Fifth Amendment to Construction Manager at Risk Contract No. 2023-17.004 for Construction Services Contract, Phase II with Jon F. Swift, Inc. in the amount of $92,757, for Hurricane Ian Repairs at the East Kayak Launch at Water Control Structure 106.

Background Information

As a result of impacts from Hurricane Ian, the kayak launch on the Snover Waterway located near water control structure 106 (east side) suffered extensive damage. As outlined in the Rostan Damage Assessment Report, damage was identified to the floating dock, floating launch, and gangway to the launch.

In consultation with City Administration the use of the Construction Manager at Risk (CMaR) Continuing Services Contract has been identified as the most expedient path to complete this project. The following describes the CMaR process specific to this project:

> April 10, 2024: Work Assignment No. 2024-34FM was issued to Jon F. Swift, Inc. for pre-construction phase (Phase 1) services. During this phase the Contractor evaluated the work required, obtained quotes from applicable contractors, and developed the Guaranteed Maximum Price (GMP).

> April 19, 2024: Jon F. Swift, Inc. submitted a Guaranteed Maximum Price (GMP) proposal. This Amendment to Contract No. 2023-17.004 presented for approval is for the construction phase (Phase 2) of the process. The Project Manager with the Department of Public Works provided a direct selection of Jon F. Swift, Inc. as the preferred CMaR to carry out the project at the Water Control Structure 106 East Kayak Launch and requests approval of this Amen...