File #: 24-0920    Version: 1 Name:
Type: Consent Agenda Status: Agenda Ready
File created: 6/18/2024 In control: City Commission Regular Meeting
On agenda: 7/9/2024 Final action:
Title: Approve First Amendment to Construction Manager at Risk Contract No. 2023-17.005 for Construction Services Contract Phase II with Willis A. Smith Construction, Inc., in the Amount of $78,032.00, for Fire Station 86 and Police Substation Repairs.
Attachments: 1. First Amendment to Contract, 2. Contract, 3. Florida Division of Corporations Document
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
TO: Honorable Mayor & Members of the North Port Commission

FROM: A. Jerome Fletcher II, ICMA-CM, MPA, City Manager

TITLE: Approve First Amendment to Construction Manager at Risk Contract No. 2023-17.005 for Construction Services Contract Phase II with Willis A. Smith Construction, Inc., in the Amount of $78,032.00, for Fire Station 86 and Police Substation Repairs.


Recommended Action

Approve First Amendment to Construction Manager at Risk Contract No. 2023-17.005 for Construction Services Contract Phase II with Willis A. Smith Construction, Inc., in the Amount of $78,032.00, for Fire Station 86 and Police Substation Repairs.

Background Information

Due to Hurricane Ian, Fire Station 86 and Police Substation was damaged by wind and water and is requiring necessary repairs. Staff continue to work with representatives from the Federal Emergency Management Agency, (FEMA), Rostan Solutions, Inc., and the insurance provider, Halliwell, to identify funding availability for reimbursement of this project.
?
Upon evaluation of the project, the use of the Construction Manager at Risk (CMaR) Continuing Services Contract has been identified as the most expedient path to complete this project. The CMaR Contracting process includes the following two phases:
?
>?????????????????????Phase One:? The Contractor is selected and issued a Work Assignment for the pre-construction phase. During this portion of the project, the contractor evaluates the work required, obtains quotes from applicable contractors, and develops the Guaranteed Maximum Price (GMP).
?
>?????????????????????Phase Two:? The First Amendment to the CMaR Contract No. 2023-17.005 is for the construction phase of the process.
?
North Port Fire Rescue and North Port Police Department provided a direct selection of Willis A. Smith Construction, Inc. as the preferred CMaR to perform the necessary repairs at Fire Station 86 and Police Substation.? Accordingly, staff requests City Commission approval of the...

Click here for full text