ACTION: Twenty-five (25) days to achieve compliance (no later than
November 17, 2025) or a $10/day fine up to a maximum of $1,000.00
beginning November 18, 2025.
Attachments:
D.
CECASE-25- (AB), Joseph & Sylvia Perry, 3372 Cunliffe Road
62-50, NPCC - Refuse container(s)
(Containers improperly placed in the front of the property.)
ACTION: Twenty-five (25) days to achieve compliance (no later than
November 17, 2025) or a $10/day fine up to a maximum of $1,000.00
beginning November 18, 2025.
42-23 NPCC - Accumulation of debris
(Debris consisting of miscellaneous items on the left side of the property in
front and rear of the property.)
ACTION: Twenty-five (25) days to achieve compliance (no later than
November 17, 2025) or a $10/day fine up to a maximum of $1,000.00
beginning November 18, 2025.
IPMC 2021, 304 Exterior Structure - 304.1 General
(Dilapidated walls in need of repair.)
ACTION: Twenty-five (25) days to achieve compliance (no later than
November 17, 2025) or a $10/day fine up to a maximum of $1,000.00
beginning November 18, 2025.
Attachments:
E.
CECASE-25- (AB), Bettr Homes Construction LLC, 5441 Ansonia Terrace
42-23 NPCC - Accumulation of Debris
(Construction debris left on the property improperly stored.)
ACTION: Twenty-five (25) days to achieve compliance (no later than
November 17, 2025) or a $10/day fine up to a maximum of $1,000.00
beginning November 18, 2025.
IPMC 2021, 304 Exterior Structure - 304.1 General
(Concrete slab is not free of plumbing and is considered an unsafe
structure.)
ACTION: Twenty-five (25) days to achieve compliance (no later than
November 17, 2025) or a $250/day fine with no maximum beginning
November 18, 2025.