File #: 23-1661    Version: 1 Name:
Type: Consent Agenda Status: Agenda Ready
File created: 11/14/2023 In control: City Commission Regular Meeting
On agenda: 2/27/2024 Final action: 2/27/2024
Title: Approve First Amendment to Contract No. 2023-28 for Road Rehabilitation Project to Preferred Materials, Inc., in the Amount of $3,724,860.26, With a Contingency of $670,474.84 for a Total Amount of $4,395,335.10, for an Additional Four (4) New Road Segments Including Toledo Blade Boulevard Phase III, South Salford Subdivision, Tihal Terrace, and Hampshire Circle, for Milling, Resurfacing, and Additional Time to Complete the Requested Work.
Attachments: 1. First Amendment to Contract, 2. Contract Agreement Amendment Form, 3. GIS Map of Additional Road Segments, 4. Preferred Materials, Inc Proposal, 5. Contract, 6. RFB 2023-28 Addenda and Solicitation, 7. September 26, 2023, Meeting Minutes, 8. Florida Division of Corporations Document
TO: Honorable Mayor & Members of the North Port Commission

FROM: A. Jerome Fletcher II, ICMA-CM, MPA, City Manager

TITLE: Approve First Amendment to Contract No. 2023-28 for Road Rehabilitation Project to Preferred Materials, Inc., in the Amount of $3,724,860.26, With a Contingency of $670,474.84 for a Total Amount of $4,395,335.10, for an Additional Four (4) New Road Segments Including Toledo Blade Boulevard Phase III, South Salford Subdivision, Tihal Terrace, and Hampshire Circle, for Milling, Resurfacing, and Additional Time to Complete the Requested Work.



Recommended Action

Approve First Amendment to Contract No. 2023-28 for Road Rehabilitation Project to Preferred Materials, Inc., in the amount of $3,724,860.26, with a contingency of $670,474.84 for a total amount of $4,395,335.10, for an additional four (4) new road segments including Toledo Blade Boulevard Phase III, South Salford Subdivision, Tihal Terrace, and Hampshire Circle, for milling, resurfacing, and additional time to complete the requested work.

Background Information

During the Governing Body of the Road and Drainage District Meeting on September 26, 2023, the Commission approved Contract No. 2023-28 Road Rehabilitation Project with Preferred Materials, Inc. in the amount of $4,397,544.80, plus contingency in the amount of $791,558.06, for a total amount of $5,189,102.86.

The Contract consists of routine road rehabilitation for roads, stormwater improvements and milling and resurfacing.

The proposed First Amendment is for an additional four (4) road segments including Toledo Blade Boulevard Phase III (from Bobcat Trail to Hillsborough Boulevard), South Salford Subdivision, Tihal Terrace and Hampshire Circle. Work will include milling and resurfacing, and additional Maintenance of Traffic (MOT) as required. This first Amendment request is in the City's best interest to execute because Preferred Materials, Inc. is already mobilized and currently doing work for the City of North Port. In...

Click here for full text