File #: 17-1105    Version: 1 Name:
Type: Presentation Status: Passed
File created: 5/30/2017 In control: City Commission Joint Meeting
On agenda: 6/6/2017 Final action: 6/6/2017
Title: Update on Butler Park Family Aquatic Center concept
Sponsors: Cheryl Greiner
Attachments: 1. Butler Park Family Aquatic Center Presentation, 2. Butler Park Pool Rendering - 5-22-2017, 3. Butler Park Pool Rendering - 5-25-2017, 4. Opinion of Probable Cost - Conceptual Design
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

TO:                                           Honorable Mayor & Members of the North Port Commission

 

FROM:                      Peter D. Lear, CPA, CGMA, Interim City Manager

 

TITLE:                     Update on Butler Park Family Aquatic Center

 

 

Recommended Action

 

Presentation on the Butler Park Family Aquatic Center conceptual plan and timeline.

 

Background Information

 

At the March 29, 2017 Commission workshop, Kimley-Horn and Associates, Inc. presented a concept for a 50M competitive pool w/ bulkheads, lazy river, support buildings (bath house, office, concessions, and pool mechanical) with pool heaters, lighting, fencing, shade, and concrete pool deck for staging and spectator seating. Additional amenities included a children’s pool, water slides, and other spray features. At that workshop, Commission determined that a more balanced aquatic facility to serve multi-generational programming would better meet the needs of the community and directed staff to work with the Consultant to develop a new concept for a family aquatic center.

 

During the May 22, 2017 Commission special meeting, Kimley-Horn and Associates, Inc. presented a revised concept that replaced the 50M competitive pool with a stretch 25-yard lap pool, incorporated a zero-depth entry to the lazy river, enhanced the children’s play pool amenities, and added water slides, spray features, shade and deck seating. Based on feedback received during that meeting, several additional changes to the design were requested and are reflected in the updated concept plan (attached) including:

 

1)                     Separated the children’s pool from the lazy river

2)                     Added wide steps for lesson programming at the lazy river

3)                     Added the shade for the bleachers

4)                     Deleted the oval canopy at the main bathhouse/entry area and made it perpendicular to get more deck space

5)                     Relocated and expanded the bowl slide and added a wet deck area at the river island

 

With the Commission’s approval at the May 22, 2017 meeting to move forward with the project as presented and discussed, the design, bidding and construction of the Butler Park Family Aquatic Center is conservatively estimated to take 730 calendar days with a tentative project schedule as follows:

 

June 2017 - Design work started

December 2017 -Plans Complete

January 2018 - Permitting Complete

February 2018 - Advertise for Bids

March 2018 - Contract Award

April 2018 - Begin Construction

May 2019 - Open to the Public

 

Strategic Plan

 

Financially responsible City providing quality municipal services

 

Financial Impact

 

Based on the conceptual design presented, Kimley-Horn & Associates, Inc. provided an opinion of probable cost for the construction in the amount of $11,400,000.00.

 

Procurement

 

 

Attachments:

1.                     Butler Park Pool Presentation

2.                     Butler Park Pool Rendering - May 22, 2017

3.                     Butler Park Pool Rendering - May 25, 2017

4.                     Opinion of Probable Cost - Conceptual Design

 

 

 

Prepared by:                                            Sandy Pfundheller

 

Department Director:                       Sandy Pfundheller, Interim General Services Director