Title: Contract No. 2019-13, Water Transmission Expansion Myakkahatchee Creek Water Treatment Plant to Ortiz Phase I with Andrew Sitework LLC., in the amount of $ 303,932 with a contingency amount of $ 30,393, for a total amount of $ 334,325.
Attachments: 1. Contract No. 2019-13 Andrew Sitework LLC, 2. Notice of Intent to Award, 3. Award Recommendations, 4. Bid Tabulation, 5. RFB Submittal by Andrew Sitework LLC, 6. RFB No. 2019-13, 7. Florida Division of Corporations Documents
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

 

 

TO:                                           Honorable Mayor & Members of the North Port Commission

 

FROM:                      Peter D. Lear, CPA, CGMA, City Manager

 

TITLE:                     Contract No. 2019-13, Water Transmission Expansion Myakkahatchee Creek Water Treatment Plant to Ortiz Phase I with Andrew Sitework LLC., in the amount of $ 303,932 with a contingency amount of $ 30,393, for a total amount of $ 334,325.

 

 

Recommended Action

 

Approve Contract No. 2019-13, Water Transmission Expansion Myakkahatchee Creek Water Treatment Plant to Ortiz Phase I with Andrew Sitework LLC., in the amount of $ 303,932 with a contingency amount of $ 30,393, for a total amount of $ 334,325.

 

Background Information

 

In order to expand the transmission capacity, the City of North Port established a multi-year project to increase the size of the water main from the Myakkahatchee Creek Water Treatment Plant to Ortiz Boulevard. The City has recently completed the construction of a 16-inch water main from the Myakkahatchee Creek Water Treatment Plant south along North Port Boulevard to just south of the bridge located at the back entrance of Winn Dixie. Currently under design is approximately 5,650 linear feet from the bridge on North Port Boulevard to Eager Street and approximately 2,200 linear feet from Grobe Street to Ortiz Boulevard. 

 

This latest project includes the construction of a 16-inch PVC water main between Eager and Grobe Streets, and the construction of approximately 70-LF of a 4-inch water main across West North Drive at Eager Street. There will be a connection to an existing 8-inch water main at Eager Street and connection to an existing 8-inch water main at Grobe Street as part of the project. The project construction incorporates all associated testing, miscellaneous work, restoration, and clean-up. This existing section of the transmission main is a severe bottleneck. The new main will connect two 12-inch main segments that are currently connected by an 8-inch main. The new main also will be ready to be connected to the mains being designed as referenced above. 

 

The Water Transmission Expansion MCWTP to Ortiz Phase I project was advertised on August 24, 2018. A non-mandatory pre-bid meeting was held on September 17, 2018. One bid was received, opened, and read on September 27, 2018 at 2:00 PM.

 

Staff has reviewed the bid and the contractor has been determined to be qualified for the project by our Engineer of record. Based on this information, Utilities Department recommends award of Contract 2019-13 to Andrew Sitework LLC.

 

Legal has reviewed the agreement and has approved it as to form and correctness. 

 

Strategic Plan

 

This project supports the City’s Strategic Plan goals of Enhanced Public Trust through Responsible City Government and Maintained/Upgraded/Expanded City Infrastructure.

 

Financial Impact

 

The amount of $ 334,325 is available in the account number below and budgeted in the respective project:

 

 

Account Number

Project

Available Amount

423-6061-533.63-00

U17WOR

$ 334,325

 

Procurement

 

This project was procured in accordance with Section 2-404 of the City Procurement Code - Competitive Sealed Bid Process

 

Vendor Information:

Andrew Sitework LLC.

2511 Palm Ave

Fort Myers, FL 33916

 

Attachments:

1.                     Contract No. 2019-13 with Andrew Sitework LLC.

2.                     Notice of Intent to Award

3.                     Award Recommendations

4.                     Bid Tabulation

5.                     RFB Submittal by Andrew Sitework LLC

6.                     RFB No. 2019-13

7.                     Florida Division of Corporations Documents

 

 

Prepared by:                                            Michelle Tipp

 

Department Director:                       Richard Newkirk