Title: Approve Award of Request for Bid 2025-38 Lazy River Resurfacing Project to Electro Mechanic Industries, LLC in the Amount of $261,484 Plus a Construction Contingency of $26,148 for an Amount Not to Exceed $287,632.
Attachments: 1. Contract No. 2025-38, 2. RFB No. 2025-38 Notice of Intent to Award, 3. RFB No. 2025-38 with all Addenda, 4. RFB No. 2025-38 Electro Mechanic Industries LLC Submittal, 5. Florida Division of Corporations
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
TO: Honorable Mayor & Members of the North Port Commission

FROM: A. Jerome Fletcher II, ICMA-CM, MPA, City Manager

TITLE: Approve Award of Request for Bid 2025-38 Lazy River Resurfacing Project to Electro Mechanic Industries, LLC in the Amount of $261,484 Plus a Construction Contingency of $26,148 for an Amount Not to Exceed $287,632.


Recommended Action

Option 1: Approve Award of Request for Bid 2025-38 Lazy River Resurfacing Project to Electro Mechanic Industries, LLC in the amount of $261,484 plus a construction contingency of $26,148 for an amount not to exceed $287,632.

City Commission Options

Option 1: Approve Award of Request for Bid 2025-38 Lazy River Resurfacing Project to Electro Mechanic Industries, LLC in the amount of $261,484 plus a construction contingency of $26,148 for an amount not to exceed $287,632.

* Pros: Resurfacing will extend the life of the Lazy River, maintaining its safety, appearance, and availability for public use; prevents further deterioration and reduces the risk of more expensive structural damage or emergency closures.
* Cons: Despite the contingency, unforeseen site conditions or material costs could lead to change orders and budget adjustments.

Option 2: Deny Award of Request for Bid 2025-38 Lazy River Resurfacing Project to Electro Mechanic Industries, LLC in the amount of $261,484 plus a construction contingency of $26,148 for an amount not to exceed $287,632.

* Pros: Funds earmarked for this project could be reallocated for other City initiatives.
* Cons: Continued surface degradation could lead to safety concerns, forcing closure of facility and reducing public satisfaction; delaying repairs may result in more extensive damage, increasing future costs and potentially requiring full reconstruction.

Background Information

The Parks & Recreation Department prepared a Request for Bid (RFB) for the North Port Aquatic Center Lazy River Resurfacing project, which was advertised on DemandStar on July 14, 2025. This bi...

Click here for full text