File #: 20-2812    Version: 1 Name:
Type: Consent Agenda Status: Agenda Ready
File created: 10/20/2020 In control: City Commission Regular Meeting
On agenda: 11/10/2020 Final action: 11/10/2020
Title: Approve Plan for Decommissioning and Removing the Fountain at Veteran's Park
Attachments: 1. Memorandum Plan for Decommissioning the Fountain at Veteran’s Park
TO: Honorable Mayor & Members of the North Port Commission

FROM: Peter D. Lear, CPA, CGMA, City Manager

TITLE: Approve Plan for Decommissioning and Removing the Fountain at Veteran's Park



Recommended Action

Approve plan for decommissioning and removing the fountain at Veteran's Park.

Background Information

During the Commission Regular Meeting held on September 8, 2020, the Commission directed staff to turn off the water to the fountain/waterfall at Veteran's Park and bring back a memo explaining how the feature will be decommissioned and removed.

Pursuant to the Commission's directive, please be advised that staff has completed the following tasks:

1. During the week of September 14, 2020, the Infrastructure and Facilities Operations and Maintenance Division staff of the Public Works Department disconnected the water to the fountain at Veteran's Park.

2. Memorandum explaining how the fountain at Veteran's Park will be decommissioned and removed was prepared. (Refer to Attachment 1).

3. Plan for Decommissioning and Removing the Fountain at Veteran's Park

A. Tasks

a) Remove the entire fountain wall and basin.
b) Fill the area with decorative rock to match the existing decorative rock.

B. Workforce to Complete Project

a) Infrastructure and Facilities Maintenance and Operations Division staff of the Department of Public Works.

C. Project Staff and Equipment Costs

Staff and Equipment Cost
Staff
Cost ($)
Equipment Operator II
160.64
Equipment Operator III
226.72
Equipment Operator III
283.20
Total Staff Cost
670.56
Equipment
COST ($)
Wheel Excavator (313)
144.24
Dump Truck
733.20
Pick-up Truck
200.00
Total Equipment Cost
1,077.44
Total Cost
1,748.00

D. Project Completion Time

a) The Project will be completed within two weeks of the Commission's approval of the
Plan for Decommissioning and Removing the Fountain at Veteran's Park.

Strategic Plan

Efficient and Effective Government

Financial Impact

The Infrastructure and Facilities Ope...