Legislation Details

File #: ORD. NO. 2026-19    Version: 1 Name:
Type: Ordinance Status: Agenda Ready
File created: 6/9/2026 In control: City Commission Regular Meeting
On agenda: 6/23/2026 Final action:
Title: An Ordinance of the City of North Port, Florida, Amending the Non-District Budget and Capital Improvement Budget for Fiscal Year 2025-2026 to Increase the Warm Mineral Springs Building Rehabilitation Project WM19BR by the Amount of $4,082,133; Providing for Findings; Providing for Posting; Providing for Conflicts; Providing for Severability; and Providing an Effective Date.
Attachments: 1. Ordinance No. 2026-19, 2. Fund Balance Reports, 3. Project #WM19BR Budget Tracking, 4. Budget Estimate - Demo & Build New Option
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
TO: Honorable Mayor & Members of the North Port Commission

FROM: A. Jerome Fletcher II, ICMA-CM, MPA, City Manager

TITLE: An Ordinance of the City of North Port, Florida, Amending the Non-District Budget and Capital Improvement Budget for Fiscal Year 2025-2026 to Increase the Warm Mineral Springs Building Rehabilitation Project WM19BR by the Amount of $4,082,133; Providing for Findings; Providing for Posting; Providing for Conflicts; Providing for Severability; and Providing an Effective Date.


Recommended Action First Reading

Option 1: Approve Ordinance No. 2026-19 as presented and move to second reading on July 7, 2026.

City Commission Options First Reading

Option 1: Approve Ordinance No. 2026-19 as presented and move to second reading on July 7, 2026.
* Pros:
o Advances the building renovation direction previously approved by the City Commission.
o Facilitates improvements that preserve the property's historic designation.
* Cons:
o Appropriates dollars available in fund balance, that will not be available for other uses.
o Reduces existing capital improvement project for the Langlais Park Development.
Option 2: Deny Ordinance No. 2026-19 as presented.
* Pros:
o Funds planned for use could be utilized for other future programs or initiatives.
* Cons:
o Delays implementation of previously directed Warm Mineral Springs building renovation work.
o May result in construction cost escalation due to schedule delays, market conditions, or inflationary impacts.
o Increases the risk of continued deterioration of historic buildings.

Background Information

The Warm Mineral Springs Building Rehabilitation Project WM19BR currently has $12,587,596 in available funding remaining. This total reflects the remaining project balance after expenditures for the Master Plan development; the Public Private Partnership (P3) process; Hurricane Ian and plumbing repairs; and all associated design, permitting and pre-construction services. The remaining funding available...