File #: 23-0039    Version: 1 Name:
Type: Consent Agenda Status: Agenda Ready
File created: 12/16/2022 In control: City Commission Regular Meeting
On agenda: 1/10/2023 Final action: 1/10/2023
Title: Approve Contract No. 2023-08 - Sumter Boulevard Utility Extensions with Spectrum Underground, Inc. in the Amount of $3,346,632.35, With a Contingency of $501,995.00, for a Total Amount of $3,848,627.35.
Attachments: 1. Contract No. 2023-08, 2. Notice of Intent to Award, 3. Award Recommendation Memo, 4. Bid Tabulation, 5. Submittal by Spectrum Underground, Inc., 6. RFB No. 2023-08 and Addendum, 7. Florida Division of Corporations Documents
TO: Honorable Mayor & Members of the North Port Commission

FROM: A. Jerome Fletcher II, ICMA-CM, MPA, City Manager

TITLE: Approve Construction Contract No. 2023-08 - Sumter Boulevard Utility Extensions with Spectrum Underground, Inc. in the Amount of $3,346,632.35, With a Contingency of $501,995.00, for a Total Amount of $3,848,627.35.


Recommended Action

Approve Construction Contract No. 2023-08 - Sumter Boulevard Utility Extensions with Spectrum Underground, Inc. in the amount of $3,346,632.35, with a contingency of $501,995.00, for a total amount of $3,848,627.35.

Background Information

To promote economic development, the City is planning to extend utility services along Sumter Boulevard and through the I-75 interchange. This project is partially funded by American Rescue Plan Act funds. The following provides a chronological order of events regarding the competitive sealed bid process for this project:

> September 9, 2022: RFB No. 2023-08 - Sumter Boulevard Utility Extensions was advertised.

> October 26, 2022: Four bids were received and opened.

> Staff reviewed the bids and the lowest, responsive bidder, Spectrum Underground, Inc. was determined to be qualified by the Project Engineer of Record, Stantec Consulting Services, Inc.

> November 2, 2022: Notice of Intent to Award RFB No. 2023-08 to Spectrum Underground was issued.

Based on the above, staff recommends the Award of Contract No. 2023-08 to Spectrum Underground, Inc.
Due to the potential for unforeseen complications with this type of a project, staff is recommending increasing the standard 10% contingency to 15% contingency of the Contract price.

Construction Contract No. 2023-08 has been reviewed by the City Attorney and is legally correct as to form.

Strategic Plan

Infrastructure & Facilities Integrity

Financial Impact

The amount of $3,848,627.35 is available in the account numbers below and budgeted in the respective project:

Account Number
Project
Available Amount

420-606...

Click here for full text