File #: 24-1289    Version: 1 Name:
Type: Consent Agenda Status: Passed
File created: 8/21/2024 In control: City Commission Regular Meeting
On agenda: 9/10/2024 Final action: 9/10/2024
Title: Approve Second Amendment to Construction Manager at Risk Contract No. 2023-17.001 for Construction Services Contract Phase II with Wharton-Smith, Inc., in the Amount of $362,321.00, for Fire Station 82 and Police Substation Repairs.
Attachments: 1. Second Amendment to Contract, 2. Contract No. 2023-17.001, 3. Florida Division of Corporations Document
TO: Honorable Mayor & Members of the North Port Commission

FROM: A. Jerome Fletcher II, ICMA-CM, MPA, City Manager

TITLE: Approve Second Amendment to Construction Manager at Risk Contract No. 2023-17.001 for Construction Services Contract Phase II with Wharton-Smith, Inc., in the Amount of $362,321.00, for Fire Station 82 and Police Substation Repairs.

Recommended Action

Approve Second Amendment to Construction Manager at Risk Contract No. 2023-17.001 for Construction Services Contract Phase II with Wharton-Smith, Inc., in the amount of $362,321.00, for Fire Station 82 and Police Substation repairs.

Background Information

Due to Hurricane Ian, Fire Station 82 and Police Substation was damaged by wind and water and requires repairs. Staff continue to work with representatives from the Federal Emergency Management Agency, (FEMA), Rostan Solutions, Inc., and the insurance provider, Halliwell, to identify funding availability for reimbursement of this project.
?
Upon evaluation of the project, the use of the Construction Manager at Risk (CMaR) Continuing Services Contract has been identified as the most expedient path to complete this project. The CMaR Contracting process includes the following two phases:
?
>?????????????????????Phase One:? The Contractor is selected and issued a Work Assignment for the pre-construction phase. During this portion of the project, the contractor evaluates the work required, obtains quotes from applicable contractors, and develops the Guaranteed Maximum Price (GMP).
?
>?????????????????????Phase Two:? The Second Amendment to the CMaR Contract No. 2023-17.001 is for the construction phase of the process.
?
Public Works provided a direct selection of Wharton-Smith, Inc. to Purchasing as the preferred CMaR to perform the necessary repairs at Fire Station 82 and Police Substation.? Accordingly, staff requests City Commission approval of the Second Amendment to CMaR Contract No. 2023-17.001 for Construction Services Contract...