TO: Honorable Mayor & Members of the North Port Commission
FROM: A. Jerome Fletcher II, ICMA-CM, MPA, City Manager
TITLE: Approve Work Assignment No. 2023-40.003 IT2-2026 - Inflow & Infiltration Rehabilitation - CIPP- Freemont Street and LS-21 with Insituform Technologies, LLC for Cured in Place Pile Lining of Areas Identified of High Inflow and Infiltration Around Freemont Street and Lift Station 21 in the Amount of $896,857.35
Recommended Action
Option 1: Approve Work Assignment No. 2023-40.003 IT2-2026 - Inflow & Infiltration Rehabilitation - CIPP - Freemont Street and LS-21 with Insituform Technologies, LLC for cured in place pile lining of areas identified of high inflow & infiltration around Freemont Street and Lift Station 21 in the Amount of $896,857.35.
Additional Commission Options
Option 1: Approve Work Assignment No. 2023-40.003 IT2-2026 - Inflow & Infiltration Rehabilitation - CIPP - Freemont Street and LS-21 with Insituform Technologies, LLC for cured in place pile lining of areas identified of high inflow & infiltration around Freemont Street and Lift Station 21 in the Amount of $896,857.35.
* Pros: Proactively line gravity mains at risk of failure while ensuring compliance with the draft Consent Order for I&I rehabilitation.
* Cons: Commits utility funds to this project, which could be used on other projects.
Option 2: Deny Work Assignment No. 2023-40.003 IT2-2026 - Inflow & Infiltration Rehabilitation - CIPP - Freemont Street and LS-21 with Insituform Technologies, LLC for cured in place pile lining of areas identified of high inflow & infiltration around Freemont Street and Lift Station 21 in the Amount of $896,857.35.
* Pros: Preserves utility funds for allocation to other utility projects.
* Cons: Denial of the Work Assignment would result in increased risk of gravity main failure and would limit the City's ability to address Inflow and Infiltration in this area.
Background Information
Inflow and infiltration (I&I) are extraneous ...