File #: 24-0684    Version: 1 Name:
Type: Consent Agenda Status: Agenda Ready
File created: 4/30/2024 In control: City Commission Regular Meeting
On agenda: 5/28/2024 Final action: 5/28/2024
Title: Approve Change Order No. 1 to Work Assignment 2022-03 for Professional Engineering Service for the Myakkahatchee Creek Surface Water Treatment Plant Intake Structures Repairs, Renovations and/or Upgrades Project with Stantec Consulting Services, Inc., for an Additional Amount of $7,935.00, for a Total Cost of $ 247,817.64
Attachments: 1. Work Assignment Change Order, 2. Work Assignment, 3. Continuing Contract No. 2020-58-12, 4. Florida Division of Corporations Documents
TO: Honorable Mayor & Members of the North Port Commission

FROM: A. Jerome Fletcher II, ICMA-CM, MPA, City Manager

TITLE: Approve Change Order No. 1 to Work Assignment 2022-03 for Professional Engineering Service for the Myakkahatchee Creek Surface Water Treatment Plant Intake Structures Repairs, Renovations and/or Upgrades Project with Stantec Consulting Services, Inc., for an Additional Amount of $ 7,935.00, for a Total Cost of $ 247,817.64


Recommended Action

Approve Change Order No. 1 to Work Assignment 2022-03 for professional engineering services for the Myakkahatchee Creek Surface Water Treatment Plant Intake Structures Repairs, Renovations and/or Upgrades Project with Stantec Consulting Services, Inc., for an additional amount of $ 7,935.00, for a total cost of $ 247,817.64.

Background Information

North Port Utilities (NPU) budgeted to rehabilitate the raw water intake structures on the Myakkahatchee Creek and the Cocoplum Waterways. The below information is the series of events pertinent to this project.

> February 10, 2022: Request for Letters of Interest (RLI) 2022-03 was issued to the eight firms under Category 1 of Continuing Contract 2020-58 to secure professional engineering services to design, bid, and provide construction phase services for the rehab of the structures.
> March 11, 2022: Three (3) Letters of Interest (LOI) were received.
> March 21, 2022: The LOIs were evaluated and Stantec Consulting Services, Inc., was selected to proceed with the development of a scope and fee schedule.
> December 8, 2023: Bid for construction was published with due date of January 9, 2024.
> December 20, 2023: Addendum No. 1 moved the original due date to January 16, 2024
> January 16, 2024: Four (4) bids were received and opened.
> January 17, 2024: Laurence Lee Construction, the apparent low bidder, withdrew their bid.
> January 23, 2024: Letter of Recommendation for award to Douglas Higgins provided by Stantec.
> March 12, 2024: Douglas Higgins...