File #: RES. NO. 2022-R-40    Version: 1 Name:
Type: Resolution Status: Agenda Ready
File created: 6/9/2022 In control: City Commission Regular Meeting
On agenda: 7/26/2022 Final action: 7/26/2022
Title: A Resolution of the City Commission of the City of North Port, Florida, Amending the Non-District Budget for Fiscal Year 2021-22 for Sanitary Trailer Rental for Warm Mineral Springs in the amount of $60,000; Providing for Findings; Providing for Conflicts; Providing for Severability: and Providing an Effective Date.
Attachments: 1. Resolution
TO: Honorable Mayor & Members of the North Port Commission

FROM: A. Jerome Fletcher II, ICMA-CM, MPA, City Manager

TITLE: A Resolution of the City Commission of the City of North Port, Florida, Amending the Non-District Budget for Fiscal Year 2021-22 for Sanitary Trailer Rental for Warm Mineral Springs in the amount of $60,000; Providing for Findings; Providing for Conflicts; Providing for Severability: and Providing an Effective Date.


Recommended Action

Approve Resolution No. 2022-R-40 on 1st Reading and move to 2nd Reading on July 26, 2022.

Recommended Action on Second Reading

Adopt Resolution No. 2022-R-40.


Background Information

Due to structural damages sustained from Tropical Storm Elsa in July 2021 the City of North Port was required to close the Warm Mineral Spring Park restroom/locker room building to the public. In order to keep the facility operational and open to the public a ten-stall restroom trailer, an American with Disabilities Act (ADA) restroom, and hand washing station were procured and located at the Warm Mineral Springs Park. Although funds were not budgeted for this expense, the available repair and maintenance budget was initially utilized. Staff intended to have the temporary restroom facilities transition to permanent restroom facilities included in a future construction contract associated with Project #WM19BR Warm Mineral Springs Restoration. However, after competitively bidding Project #WM19BR, the sole bid received was nearly double the funds allocated for this project. As such, during the City Commission Budget Workshop held on June 16, 2022, the Commission provided the following consensuses:

> Consensus for staff to get with Kimley Horn for cost of Phase 1A which is the utilities on Ortiz and Trionfo in the Springs and Building 2 at a special meeting for action sooner rather than later.

> Consensus to have staff proceed pursuing a P3 partner.

Staff was directed by the Commission to fund the rental restrooms through ...

Click here for full text