TO: Honorable Mayor & Members of the North Port Commission
FROM: A. Jerome Fletcher II, ICMA-CM, MPA, City Manager
TITLE: Approve the Sixteenth Amendment to Construction Manager at Risk Contract No. 2023-17.002 for Construction Services Contract, Phase II With Halfacre Construction Company in the Amount of $35,868.68, for Hurricane Ian Repairs at LaBrea Park.
Recommended Action
Approve the Sixteenth Amendment to Construction Manager at Risk Contract No. 2023-17.002 for Construction Services Contract, Phase II with Halfacre Construction Company in the amount of $35,868.68, for Hurricane Ian Repairs at LaBrea Park.
Background Information
As a result of impacts from Hurricane Ian, LaBrea Park suffered damage to the site fencing, signage, playground equipment, shade canopies, and trash receptacles as outlined in the Halliwell Construction Services and Rostan Damage Assessment Report. While initial repairs were underway at LaBrea Park, Halfacre Construction Company and City staff discovered that the two (2) shade structures had sustained structural damage beyond the repairs assumed in the GMP allowance outlined in the Fifth Amendment to contract 2023-17.002. In order to return the park to its pre-hurricane condition, both shade structures require full replacement.
In consultation with City Administration, the use of the Construction Manager at Risk (CMaR) Continuing Services Contract has been identified as the most expedient path to complete this project. The following describes the CMaR process specific to this project:
> September 24, 2024: Fifth Amendment to Contract No. 2023-17.002 encompassing Work Assignment No. 2024-06FM was issued to Halfacre Construction Company for Pre-Construction Phase (Phase I) services. During this phase, the Contractor evaluated the work required, obtained quotes from applicable contractors, and developed the Guaranteed Maximum Price (GMP).
> February 7, 2025: Halfacre Construction Company submitted a GMP for additional ser...