TO: Honorable Mayor & Members of the North Port Commission
FROM: A. Jerome Fletcher II, City Manager
TITLE: Consideration of PLF-21-200, Wellen Park Village E Final Plat (QUASI-JUDICIAL).
Recommended Action
City Commission approve Petition No. PLF-21-200, Wellen Park Village E Final Plat.
Background Information
John E. Luczynski, Senior Vice-President, Land Development Wellen Park, LLLP on behalf of Manasota Beach Ranchlands, LLLP requests review and approval of a Final Plat for 21 separate tracts within Village E of Wellen Park.
In September of 2020 the Master Infrastructure Plans (INF-20-074) for Village E of Wellen Park were approved by City staff. Additional roadway infrastructure plans for Merlot Drive and Mezzo Drive extensions (INF-19-208 & INF-21-191) were also approved by City staff in December of 2019 and August of 2021 respectively. This Project is platting 21 separate tracts and the rights of way on the land currently comprising Wellen Park Village E, as well as the associated stormwater and wetland preservation tracts, utility tracts, and easements. The total site contains approximately ? 326.56 acres.
The West Villages Improvement District (WVID) has reviewed and approved the Final Plat.
A Surety Bond for INF-19-208 in the amount of $7,977,227.83 and an additional Surety Bond for INF-21-191 in the amount of $111,211.00 have both been received by the City of North Port. No bond was collected for the Village E Master Infrastructure Plan as there was no built construction associated with the project.
The Final Plat has been reviewed and approved by the City Surveyor.
During their Regular Meeting held on October 21, 2021, the Planning and Zoning Advisory Board reviewed and considered Petition No. PLF-21-200, Wellen Park Village E Final Plat. The applicant requested the following two additional changes to the Final Plat on the record:
1. A scrivener's error correcting the acreage of Tract 6 to 320,924 square-feet.
2. Revise the plat t...
Click here for full text