TO: Honorable Mayor & Members of the North Port Commission
FROM: Peter D. Lear, CPA, CGMA, City Manager
TITLE: Approve Contract Nos. 2020.41.001 through 2020.41.003 for Inflow and Infiltration Rehabilitation with Engineered Coating Solutions, Instituform Technologies, LLC and Hinterland Group, Inc. in Accordance with Unit Prices and on an As-Needed Basis; and Authorize the City Manager to Authorize Work Assignments As-Needed, Based on the Approved Budget.
Recommended Action
Approve Contract Nos. 2020.41.001 through 2020.41.003 for Inflow and Infiltration Rehabilitation with Engineered Coating Solutions, Instituform Technologies, LLC and Hinterland Group, Inc. in accordance with unit prices and on an as-needed basis; and authorize the City Manager to authorize work assignments as-needed, based on the approved budget.
Background Information
Inflow and infiltration (I&I) are extraneous flows that enter the wastewater collection system and flow through to treatment facilities. These flows reduce the capacity of the system and can lead to sanitary sewer overflows. Inflow occurs when storm water enters the sewer system through flooding of manholes and direct connections of storm water to the wastewater collection system. Infiltration occurs when groundwater and storm water enter into the wastewater collection system as a result of physical defects such as cracked pipes, leaking manholes or deteriorated joints. Most of the I&I experienced in the City is a result of infiltration and the ongoing I&I Rehabilitation Project is designed to mitigate this infiltration.
The Inflow and Infiltration Rehabilitation Project was advertised on June 12, 2020 to secure the services of one or more licensed and qualified contractors to provide as needed I&I rehabilitation services, including sewer line cleaning, gravity sewer smoke testing, manhole rehabilitation, manhole lining systems, cured-in-place pipe lining and spot repairs, grouting lateral connections, and post reha...