Title: Approve the Tenth Amendment to Agreement No. 2015-19, Professional Engineering Services for the Widening of Price Boulevard, From Sumter Boulevard to Toledo Blade Boulevard by and Between the City of North Port, Florida, and Consor North America, Inc. in the Amount of $295,796.50.
Attachments: 1. Amendment Ten to Agreement, 2. Purchasing Form, 3. Amendment Nine to Agreement, 4. Amendment Eight to Agreement, 5. Amendment Seven to Agreement, 6. Amendment Six to Agreement, 7. Amendment Five to Agreement, 8. Amendment Four to Agreement, 9. Amendment Three to Agreement, 10. Amendment Two to Agreement, 11. Amendment One to Agreement, 12. Agreement, 13. Notice of Name Change, 14. Florida Division of Corporations Document
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
TO: Honorable Mayor & Members of the North Port Commission

FROM: A. Jerome Fletcher II, ICMA-CM, MPA, City Manager

TITLE: Approve the Tenth Amendment to Agreement No. 2015-19, Professional Engineering Services for the Widening of Price Boulevard, From Sumter Boulevard to Toledo Blade Boulevard by and Between the City of North Port, Florida, and Consor North America, Inc. in the Amount of $295,796.50.


Recommended Action

Option 1: Approve the Tenth Amendment to Agreement No. 2015-19, Professional Engineering Services for the Widening of Price Boulevard, from Sumter Boulevard to Toledo Blade Boulevard by and between the City of North Port, Florida, and Consor North America, Inc. in the amount of $295,796.50.

Additional Commission Options

Option 1: Approve the Tenth Amendment to Agreement No. 2015-19, Professional Engineering Services for the Widening of Price Boulevard, from Sumter Boulevard to Toledo Blade Boulevard by and between the City of North Port, Florida, and Consor North America, Inc. in the amount of $295,796.50.

* Pros: Roadway lighting improvements will be provided along the road widening project limits, bringing this road segment up to the Florida Department of Transportation (FDOT) Greenbook roadway lighting standards and improving safety.
* Cons: The cost associated with designing and constructing the lighting improvements may limit funding available for other projects or infrastructure needs.

Option 2: Deny the Tenth Amendment to Agreement No. 2015-19, Professional Engineering Services for the Widening of Price Boulevard, from Sumter Boulevard to Toledo Blade Boulevard by and between the City of North Port, Florida, and Consor North America, Inc. in the amount of $295,796.50.

* Pros: Preserves funding for other projects or infrastructure needs.
* Cons: The widened segment of roadway will not be in conformance with the latest FDOT Greenbook roadway lighting standards, presenting a safety deficiency along the corridor.

Background Inform...