TO: Honorable Mayor & Members of the North Port Commission
FROM: A. Jerome Fletcher II, ICMA-CM, MPA, City Manager
TITLE: Approve Work Assignment No. 2023-40.003 IT3-2026 - Inflow & Infiltration Rehabilitation Cured In Place Pipe (CIPP) Lining - Freemont Avenue and Lift Station #19 with Insituform Technologies, LLC for Cured in Place Pipe Lining of Areas Identified of High Flow Inflow & Infiltration Around Freemont Avenue and Lift Station 19 in the Amount of $252,684.90.
Recommended Action
Option 1: Approve Work Assignment No. 2023-40.003 IT3-2026 - Inflow & Infiltration Rehabilitation CIPP Lining - Freemont Avenue and LS #19 with Insituform Technologies, LLC for cured in place pipe lining of areas identified of high flow Inflow & Infiltration around Freemont Avenue and Lift Station 19 in the amount of $252,684.90.
Additional Commission Options
Option 1: Approve Work Assignment No. 2023-40.003 IT3-2026 - Inflow & Infiltration Rehabilitation CIPP Lining - Freemont Avenue and LS #19 with Insituform Technologies, LLC for cured in place pipe lining of areas identified of high flow Inflow & Infiltration around Freemont Avenue and Lift Station 19 in the amount of $252,684.90.
Pros: Proactively line gravity mains at risk of failure while ensuring compliance with the Consent Order for Inflow & Infiltration rehabilitation.
Cons: Commits utility funds to this project, which could be used on other projects.
Option 2: Deny Work Assignment No. 2023-40.003 IT3-2026 - Inflow & Infiltration Rehabilitation CIPP Lining- Freemont Avenue and LS #19 with Insituform Technologies, LLC for cured in place pipe lining of areas identified of high flow Inflow & Infiltration around Freemont Avenue and Lift Station 19 in the amount of $252,684.90.
Pros: Preserves utility funds for allocation to other utility projects.
Cons: Denial of the work assignment would result in non-compliance with the Consent Order and increase the risk of gravity main failure.
Background Information