TO: Honorable Mayor & Members of the North Port Commission
FROM: A. Jerome Fletcher II, ICMA-CM, MPA, City Manager
TITLE: Discussion and Possible Action Regarding the Request from WPC, on Behalf of Avella North Port, for an Exception by Special Permit to the City of North Port Noise Ordinance to Allow Eight Early Morning Concrete Placements Between December 2026 and January 2027.
Recommended Action
Review and take action on the request from WPC, on behalf of Avella North Port, for an exception by special permit pursuant to Section 46-45(a) of the Code of the City of North Port, Florida, to allow eight (8) concrete placements outside the hours permitted by Section 46-42(6).
City Commission Options
Option 1: Approve the request for an exception by special permit, subject to conditions established by the City Commission.
• Pros: Allows the contractor to conduct concrete placements during periods of reduced traffic volume, potentially minimizing traffic congestion and interruptions to continuous concrete placement operations.
• Cons: Early morning construction activities, including equipment setup, concrete truck deliveries, lighting, and associated operations, may create noise and other disturbances for surrounding residential properties.
Option 2: Deny the request for an exception by special permit.
• Pros: Maintains the existing noise ordinance restrictions and limits construction-related disturbances during overnight and early morning hours.
• Cons: Requires the contractor to conduct construction activities within otherwise permissible hours, which the applicant indicates may increase traffic conflicts, complicate concrete delivery scheduling, and affect construction operations.
Option 3: Approve the request with modifications to the proposed schedule, authorized activities, or additional conditions intended to minimize impacts on surrounding properties.
• Pros: Provides flexibility to accommodate certain construction activities while allowing the Commission to establish limitations addressing the surrounding residential neighborhood.
• Cons: Modified hours or additional requirements may affect the contractor's proposed construction schedule and operational approach.
Background Information
Section 46-42(6) of the Code of the City of North Port, Florida prohibits the operating or permitting the operation of any tools or equipment used in construction, drilling, repair, alteration or demolition work between the hours of 9:00 p.m. and 7:00 a.m. the following day on weekdays or 9:00 p.m. and 7:30 a.m. on weekends and holidays in or within 50 yards of any residential area or noise-sensitive zone, except for emergency work by public service utilities or by a variance approved by the city commission.
On November 5, 2026, WPC submitted a request on behalf of the Avella North Port project seeking authorization to perform eight (8) concrete placements outside the hours established by the City's noise ordinance.
The applicant requests authorization for seven (7) concrete placements beginning at 3:00 a.m. and one (1) placement beginning at 5:00 a.m. The proposed work would occur on eight (8) separate dates between December 2026 and January 2027, with equipment mobilization anticipated approximately 45 minutes before each placement. The applicant has identified alternative dates to accommodate weather, supplier availability, and construction coordination.
The Code of the City of North Port, Florida, Article II, Division 2. Noise, Section 46-45, authorizes the City Commission to allow activities that would otherwise be in violation of Division 2 upon the following:
• Showing of good cause;
• Specifying the duration for which such noncompliance shall be permitted;
• Prescribing the conditions or requirements necessary to minimize adverse effects upon the community or surrounding neighborhood.
In support of the request, the applicant identifies the following considerations:
• Traffic and Public Safety: The applicant indicates that scheduling concrete deliveries during early morning hours would reduce conflicts between heavy construction vehicles and peak commuting and school-related traffic.
• Construction Operations: The applicant states that large concrete placements require continuous deliveries and coordinated operations to maintain concrete quality and structural integrity. Delays or interruptions may result in rejected material, construction deficiencies, or additional work.
• Potential Hardship: The applicant indicates that restricting the work to normal construction hours could create scheduling challenges, additional costs, material waste, or project delays.
These considerations are presented as provided by the applicant for the City Commission's evaluation in determining whether good cause exists.
Strategic Plan Pillar
Economic Development and Growth Management
Financial Impact
Not applicable
Procurement
Not applicable
Attachments:
1. Request Letter
Prepared by: Tricia Wisner, Assistant City Manager
Department Director: Tricia Wisner, Assistant City Manager