TO: Honorable Mayor & Members of the North Port Commission
FROM: A. Jerome Fletcher II, ICMA-CM, MPA, City Manager
TITLE: Discussion and Possible Action to Approve the Sixth Amendment to Construction Manager at Risk Contract No. 2023-17.001 for Construction Services Contract Phase II with Wharton-Smith, Inc., in the Amount of $332,217.00, for Repairs to the Senior Center.
Recommended Action
Approve Sixth Amendment to Construction Manager at Risk Contract No. 2023-17.001 for Construction Services Contract Phase II with Wharton-Smith, Inc., in the amount of $332,217.00, for repairs to the Senior Center.
Background Information
Due to Hurricane Ian, the Senior Center sustained damages and requires repairs. Staff has continued to work with representatives from the Federal Emergency Management Agency, (FEMA), Rostan Solutions, Inc., and the City insurance provider, Halliwell, to identify funding availability for reimbursement of this project.
Upon evaluation of the project, the use of the Construction Manager at Risk (CMaR) Continuing Services Contract has been identified as the most expedient path to complete this project. The CMaR Contracting process includes the following two phases:
Ø Phase One: The Contractor is selected and issued a Work Assignment for the Pre-Construction Phase. During this portion of the project, the contractor evaluates the work required, obtains quotes from applicable contractors, and develops the Guaranteed Maximum Price (GMP).
Ø Phase Two: The Sixth Amendment to the CMaR Contract No. 2023-17.001 is for the Construction Phase of the process.
The Department of Public Works provided a direct selection of Wharton-Smith, Inc., as the preferred CMaR to perform the repair services to the Senior Center. Accordingly, staff requests City Commission approval of the Sixth Amendment to CMaR Contract No. 2023-17.001 for Construction Services Contract Phase II with Wharton-Smith, Inc., in the amount of $332,217.00.
Work Scope Cost by Facility and Site:
Facility Site |
Amount |
Senior Center |
$332,217.00 |
|
|
Subtotal |
$332,217.00 |
The Sixth Amendment to Construction Manager at Risk Contract No. 2023-17.001 has been reviewed by the City Attorney and is legally correct as to form.
Strategic Plan
Infrastructure & Facilities Integrity
Safe Community
Financial Impact
Funding in the amount of $332,217.00 is contingent upon adoption of Ordinance 2025-01 and will be allocated in the Fiscal Year 2025 budget in Project No. IAN22, account number 001-0760-519.46-04.
Procurement
Phase II - Repair Services of the Senior Center Construction Manager at Risk Contract No. 2023-17.001 was procured pursuant Chapter 2 Administration, Article VIII Procurement, Section 2-406 Professional services selection under Consultants’ Competitive Negotiation Act (CCNA), F.S. § 287.055 of the Code of the City of North Port, Florida.
Attachments:
1. Amendment No. 6
2. Contract
3. Florida Division of Corporations Document
Prepared by: Garrett Woods, Senior Business Manager
Department Director: Chuck Speake, Public Works Director