File #: 21-0253    Version: 1 Name:
Type: Consent Agenda Status: Agenda Ready
File created: 2/3/2021 In control: City Commission Regular Meeting
On agenda: 3/2/2021 Final action: 3/2/2021
Title: Approve Work Assignment 2021-01 with Infrastructure Solution Services, LLC. for $196,770.00, for the Water Pipeline Bridge Replacements at Haberland Boulevard/Woodhaven/North Toledo Blade Boulevard/Ortiz Boulevard Project
Attachments: 1. Work Assignment No. 2021-01 with Scope and Fee Schedule, 2. RLI 2021-01 Evaluation & Ranking, 3. Infrastructure Solution Services, LLC. Letter of Interest Submittal, 4. Request for Letters of Interest 2021-01, 5. Continuing Contract No. 2020-58-08 with Infrastructure Solution Services, LLC., 6. Florida Division of Corporations Documents

TO:                                           Honorable Mayor & Members of the North Port Commission

 

FROM:                      Jason Yarborough, ICMA-CM, Interim City Manager

 

TITLE:                     Approve Work Assignment 2021-01 with Infrastructure Solution Services, LLC. for $196,770.00, for the Water Pipeline Bridge Replacements at Haberland Boulevard/Woodhaven Drive/North Toledo Blade Boulevard/Ortiz Boulevard Project.

 

 

Recommended Action

 

Approve Work Assignment 2021-01 with Infrastructure Solution Services, LLC. for $196,770.00, for the Water Pipeline Bridge Replacements at Haberland Boulevard/Woodhaven Drive/North Toledo Blade Boulevard/Ortiz Boulevard Project.

 

Background Information

 

The Department of Utilities has instituted a program to improve distribution system reliability and reduce unnecessary water loss by replacing infrastructure that has reached the end of its useful service life.  As part of this program, the Department of Utilities is replacing the welded steel water mains affixed to bridges throughout the City in a prioritized manner. In the next phase of this program, the pipelines affixed to the bridges along Haberland Boulevard, Woodhaven Drive and North Toledo Blade Boulevard have been identified as in need of replacement.

 

In addition, Sarasota County has a Bridge Replacement Project on Ortiz Boulevard.  In conjunction with this project, the Department of Utilities is planning to replace the watermain affixed to the bridge on Ortiz Boulevard. In order to achieve project savings, the Department of Utilities intends to have all four bridges designed by the same Consultant.

 

A Request for Letters of Interest (RLI) 2021-01 was issued on October 1, 2020, to the eight firms under Category 2 of Continuing Services Contract 2020-58 to secure professional engineering services to design, bid and provide construction phase services for the replacement of the water mains at the four bridges. Eight Letters of Interest were received.  Staff evaluated each Letter of Interest based on the following criteria:

 

§                     Understanding of Project deliverables

§                     Expertise and qualifications and availability of personnel

§                     Timeline, evaluations, and experience on Utility Projects

§                     Proposed cost saving measures

§                     References and required forms

 

Based on these established criteria, Infrastructure Solution Services, LLC. was selected to proceed with development of a Scope and Fee Schedule and submit to the Department of Utilities by December 16, 2020. After careful review and revisions of the Scope and Fee Schedule submitted, the Department of Utilities recommends that Infrastructure Solution Services, LLC. be awarded the Work Assignment for this Project.

 

Strategic Plan

 

Develop and promote City governance that fosters trust and utilizes departmental strengths and innovative philosophies to facilitate effective and efficient provision of all City services.

 

Financial Impact

 

The amount of $196,770.00 is available in the account number below and budgeted in the respective project:

 

Account Number

Project

Available Amount

306-6061-533.63-00

U20WBR

$146,770.00

423-6061-533.63-00

U21WMS

$5,000.00

420-6061-533.63-00

U21WMS

$45,000.00

 

 

 

 

 

 

 

Procurement

 

Continuing Contract No. 2020-58-08 was procured pursuant to Section 2-406 Professional services selection under Consultants’ Competitive Negotiation Act (CCNA), Florida Statute § 287.055. Work Assignment No. 2021-01 was issued under Continuing Contract No. 2020-58-08.

Vendor Information: Infrastructure Solution Services

7319 Merchant Court, Sarasota, FL 34240

Phone: (941) 526-0813

 

Attachments:

1.                     Work Assignment No. 2021-01 with Scope and Fee Schedule

2.                     RLI 2021-01 Evaluation & Ranking

3.                     Infrastructure Solution Services, LLC. Letter of Interest Submittal

4.                     Request for Letters of Interest 2021-01 

5.                     Continuing Contract No. 2020-58-08 with Infrastructure Solution Services, LLC.

6.                     Florida Division of Corporations Documents

 

Prepared by:                                            Nicole Brown, Business Services Coordinator

 

Department Director:                       Richard Newkirk, Utilities Director