File #: 24-0065    Version: 1 Name:
Type: Consent Agenda Status: Passed
File created: 1/3/2024 In control: City Commission Regular Meeting
On agenda: 2/27/2024 Final action: 2/27/2024
Title: Approve Eighth Amendment to Agreement No. 2015-19, Professional Engineering Services for the Widening of Price Boulevard, from Sumter Boulevard to Toledo Blade Boulevard to Consor Engineers, LLC in the Amount of $218,988.00.
Attachments: 1. Agreement, 2. Amendment Eight to Agreement, 3. Amendment Seven to Agreement, 4. Amendment Six to Agreement, 5. Amendment Five to Agreement, 6. Amendment Four to Agreement, 7. Amendment Three to Agreement, 8. Amendment Two to Agreement, 9. Amendment One to Agreement, 10. Purchasing Document for Amendment Eight to Agreement, 11. Notice of Name Change, 12. Florida Division of Corporations Document

TO:                                           Honorable Mayor & Members of the North Port Commission

 

FROM:                      A. Jerome Fletcher II, ICMA-CM, MPA, City Manager

 

TITLE:                     Approve Eighth Amendment to Agreement No. 2015-19, Professional Engineering Services for the Widening of Price Boulevard, from Sumter Boulevard to Toledo Blade Boulevard to Consor Engineers, LLC in the Amount of $218,988.00.

 

 

Recommended Action

 

Approve Eighth Amendment to Agreement No. 2015-19, Professional Engineering Services for the Widening of Price Boulevard, from Sumter Boulevard to Toledo Blade Boulevard to Consor Engineers, LLC (previously American Consulting Engineers of Florida, LLC) in the amount of $218,988.00.

 

Background Information

 

On September 28, 2015, the City of North Port entered into Agreement No. 2015-19 with American Consulting Engineers of Florida, LLC for professional engineering services to design and produce plans for the Price Boulevard Widening Project.

 

Amendment Six to Agreement No. 2015-19, approved by City Commission on January 24, 2023, added to the scope of work the design of a replacement for the bridge carrying Price Boulevard over the Myakkahatchee Creek. The design for this bridge is currently in progress. However, the current design limits leave an approximately 1,500-foot gap of two-lane road between the four-lane bridge and the four-lane intersection of Price Boulevard at Sumter Boulevard. This eighth amendment expands the scope of the project to complete the road and drainage design for this gap, resulting in a more efficient design process and the ability to utilize the full four-lane capacity of the replacement bridge. Upon completion of the Price Boulevard widening project, Price Boulevard will have a continuous four-lane section between the Myakkahatchee Creek and Toledo Blade Boulevard.

 

The cost of the additional work is $218,988.00. This amendment will only affect the Myakkahatchee Creek bridge portion of the design and will have no impact to the timeline of the widening of Price Boulevard between Sumter Boulevard and Toledo Blade Boulevard.

 

On January 1, 2024, the City was notified that American Consulting Engineers of Florida, LLC, was changing to Consor Engineers, LLC and the Contract is being assigned to Consor Engineers, LLC.

 

Approval of this Eighth Amendment to Agreement No. 2015-19 will bring the Agreement total to $4,549,335.97.

 

Amendment Eight to Agreement No. 2015-19 has been reviewed by the City Attorney and is legally correct as to form.

 

Strategic Plan

 

Infrastructure & Facilities Integrity

 

Financial Impact

 

Funding in the amount of $218,988.00 has been allocated in the Fiscal Year 2024 Road and Drainage District Budget, Project Number R15PW1 account number 144-5000-541.31-05.

 

Procurement

 

Professional Engineering Services were procured, for Contract 2015-19, pursuant to Chapter 2 Administration, Article VIII Procurement, Section 2-406 - Professional services selection under Consultants’ Competitive Negotiation Act (CCNA), F.S. §287.055 of the Code of the City of North Port, Florida.

 

Consor Engineers, LLC

155 North Wacker Drive

Suite 4150

Chicago, IL 60606

 

Attachments:

1.                                          Agreement No. 2015-19

2.                                          Amendment Eight to Agreement No. 2015-19

3.                                          Amendment Seven to Agreement No. 2015-19

4.                                          Amendment Six to Agreement No. 2015-19

5.                                          Amendment Five to Agreement No. 2015-19

6.                                          Amendment Four to Agreement No. 2015-19

7.                                          Amendment Three to Agreement 2015-19

8.                                          Amendment Two to Agreement 2015-19

9.                                          Amendment One to Agreement 2015-19

10.                                          Purchasing Document for Amendment Eight to Agreement 2015-19

11.                                          Notice of Name Change

12.                                          Florida Division of Corporations Document

 

 

 

Prepared by:                                            Anthony Friedman, P.E., PTOE, Transportation Engineer

 

Department Director:                       Chuck Speake, Public Works Director