File #: 22-3649    Version: 1 Name:
Type: Consent Agenda Status: Agenda Ready
File created: 10/18/2022 In control: City Commission Regular Meeting
On agenda: 11/8/2022 Final action: 11/8/2022
Title: Approve Contract No. 2022-35 for the Construction of the Marina Park Restrooms With C & T Contracting Services, LLC in the Amount of $187,770, Plus a Construction Contingency of $7,460, for an Estimated Construction Amount of $195,230.
Sponsors: Cheryl Greiner
Attachments: 1. Contract 2022-35, 2. Notice of Intent, 3. Award Recommendation, 4. Bid Schedule Comparison, 5. C & T Submittal, 6. Bid Document with Addenda, 7. Construction Plans, 8. Marina Park CIP, 9. Florida Dept of Corporations

TO:                                           Honorable Mayor & Members of the North Port Commission

 

FROM:                      A. Jerome Fletcher II, ICMA-CM, MPA, City Manager

 

TITLE:                     Approve Contract No. 2022-35 for the Construction of the Marina Park Restrooms With C & T Contracting Services, LLC in the Amount of $187,770, Plus a Construction Contingency of $7,460, for an Estimated Construction Amount of $195,230.

 

 

Recommended Action

 

Approve Contract No. 2022-35 for the construction of the Marina Park restrooms with C & T Contracting Services, LLC, in the amount of $187,770 plus a construction contingency of $7,460 for an estimated construction amount of $195,230.

 

Background Information

 

Request for Bid (RFB) No. 2022-35 was issued on July 21, 2022, for construction of the Marina Park restrooms.  Four (4) bids were received from C & T Contracting Services, LLC of Tampa, Qualis General Contractors, LLC of Tampa, Florida, A2 Group Inc., and Kloote Contracting Inc (which was deemed non-responsive) and opened on August 22, 2022.  Of the four bids, C & T Contracting Services, LLC was deemed the lowest responsive, responsible bidder. It is the intent to provide an ADA compliant, prefabricated concrete restroom and related site improvements at Marina Park. Water, sewer, and power are available; connections to which will be the responsibility of the contractor.

 

The City Attorney has reviewed Contract No. 2022-35 and it is legally correct as to form.

 

Strategic Plan

 

Quality of Life

 

Financial Impact

 

The construction of the Marina Park restrooms project is funded in the Fiscal Year 2023 budget, under Project Number P20MPR in the amount of $205,000 ($202,230 available to date), as reflected in account number 306-3036-572-63-00 Surtax.

 

Procurement

 

RFB No. 2022-35 is procured pursuant to Chapter 2 - Administration, Article VIII - Procurement Section 2-404 - Competitive Sealed Bid Process, of the Code of the City of North Port, Florida.

 

C & T Contracting Services, LLC

11023 Countryway Boulevard

Tampa, FL 33626

 

Attachments:

1.                     Contract No. 2022-35

2.                     RFB 2022-35 Notice of Intent

3.                     RFB 2022-35 Award Recommendation

4.                     RFB 2022-35 Bid Schedule Comparison

5.                     RFB 2022-35 C&T Submittal

6.                     RFB 2022-35 Bid document with Addenda

7.                     RFB 2022-35 Construction Plans

8.                     Marina Park CIP

9.                     Florida Division of Corporations Document

 

 

 

Prepared by:                                            Cheryl Greiner, Business Services Coordinator

 

Department Director:                       Sandy Pfundheller, Director, Parks and Recreation Department