File #: 24-1455    Version: 1 Name:
Type: Consent Agenda Status: Agenda Ready
File created: 9/18/2024 In control: City Commission Regular Meeting
On agenda: 11/12/2024 Final action:
Title: Approve Work Assignment No. 1 With Miller Pipeline, LLC., in the Amount of $599,649.90, for the Inflow and Infiltration Rehabilitation Project Under Contract 2023-40.003.
Attachments: 1. Work Assignment No. 1 with Scope and Fee Schedule, 2. Miller Pipeline, LLC Contract 2023-40.003, 3. Request for Bid 2023-40 Award Recommendation, 4. Request for Bid 2023-40, 5. Florida Division of Corporations Documents

TO:                                           Honorable Mayor & Members of the North Port Commission

 

FROM:                      A. Jerome Fletcher II, ICMA-CM, MPA, City Manager

 

TITLE:                     Approve Work Assignment No. 1 With Miller Pipeline, LLC., in the Amount of $599,649.90, for the Inflow and Infiltration Rehabilitation Project Under Contract 2023-40.003.

 

 

Recommended Action

 

Approve Work Assignment No. 1 with Miller Pipeline, LLC., in the amount of $599,649.90, for the Inflow and Infiltration Rehabilitation Project under Contract 2023-40.003.

 

Background Information

 

Inflow and infiltration (I&I) are extraneous flows that enter the wastewater collection system and flow through to the Wastewater Treatment Plant. These flows reduce the capacity of the system and can lead to sanitary sewer overflows. Inflow occurs when stormwater enters the sewer system through flooding of the manholes and direct connections of stormwater to the wastewater collection system. Infiltration occurs when groundwater and stormwater enter into wastewater collection system as a result of physical defects such as cracked pipes, leaking manholes or deteriorated joints. Most of the I&I experienced by the City is a result of infiltration and this I&I Rehabilitation Project is designed to mitigate that infiltration. This Work Assignment for the I&I Rehabilitation Project includes wastewater cured in place lining, reinstatement of service lateral connections, and sealing service lateral connections in the Holiday Park area. The following provdes a chronological order of events pertinent to the procurement of the I&I Contracts:

 

Ø                     June 2, 2022:  Request for Bid (RFB) 2023-40 for the Inflow and Infiltration Rehabilitation Project was issued to secure Contractors for as-needed I&I Rehabilitation services for the project.

 

Ø                     July 11, 2023:  Seven (7) bids were received at Bid Opening.

 

Ø                     August 11, 2023: Staff reviewed the bids and checked references for Engineered Coating Solutions, Atlantic Pipe Services, LLC, Miller Pipeline, LLC, and National Water Main Cleaning Company, and all contractors have been determined to be qualified to provide these services.

 

Ø                     November 28, 2023: Four (4) Contracts were awarded based on qualifications with Work Assignments being issued based on unit pricing, as needed.

 

After careful review of the scope and fee for the Project, the Department of Utilities recommends Miller Pipeline, LLC. be awarded Work Assignment No. 1 under Contract 2023-40.003 for this project, in the amount of $599,649.90.

 

Strategic Plan

 

Infrastructure & Facilities Integrity

Good Governance

 

Financial Impact

 

The amount of $599,649.90 is available in the Department of Utilities Fiscal Year 2024 budget, account number below and budgeted in the respective project:

 

Account Number

Project

Available Amount

420-6063-536.63-00

U24I&I

$599,649.90

 

 

 

 

 

Procurement

 

The Inflow and Infiltration Rehabilitation Project was procured pursuant to Section 2-404 of the City of North Port Procurement Code - Competitive Sealed Bid Process.

 

 

Attachments:

1.                     Work Assignment No. 1 with Scope and Fee Schedule

2.                     Miller Pipeline, LLC Contract 2023-40.003

3.                     Request for Bid 2023-40 Award Recommendation

4.                     Request for Bid 2023-40 

5.                     Florida Division of Corporations Documents

 

Prepared by:                                            Melissa McConnell, Project Manager

 

Department Director:                       Nancy Gallinaro, Utilities Director