File #: 24-1150    Version: 1 Name:
Type: General Business Status: Agenda Ready
File created: 7/19/2024 In control: City Commission Regular Meeting
On agenda: 1/28/2025 Final action:
Title: Discussion and Possible Action to Approve the Eighth Amendment to Construction Manager at Risk Contract No. 2023-17.001 for Construction Services Contract Phase II with Wharton-Smith, Inc., in the Amount of $204,679.00, for Repair Services at the Family Service Center Building.
Attachments: 1. Contract Amendment No. 8, 2. Contract, 3. Florida Division of Corporations Document
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

TO:                                           Honorable Mayor & Members of the North Port Commission

 

FROM:                      A. Jerome Fletcher II, ICMA-CM, MPA, City Manager

 

TITLE:                     Discussion and Possible Action to Approve the Eighth Amendment to Construction Manager at Risk Contract No. 2023-17.001 for Construction Services Contract Phase II with Wharton-Smith, Inc., in the Amount of $204,679.00, for Repair Services at the Family Service Center Building.

 

 

Recommended Action

 

Approve Eighth Amendment to Construction Manager at Risk Contract No. 2023-17.001 for Construction Services Contract Phase II with Wharton-Smith, Inc., in the amount of $204,679.00, for repair services at the Family Service Center Building.

 

Background Information

 

Due to Hurricane Ian, the Family Service Center Building sustained significant damage and repairs are required. Staff has continued to work with representatives from the Federal Emergency Management Agency, (FEMA), Rostan Solutions, Inc., and the City insurance provider, Halliwell, to identify funding availability for reimbursement of this project.

 

Upon evaluation of the project, the use of the Construction Manager at Risk (CMaR) Continuing Services Contract has been identified as the most expedient path to complete this project. The CMaR contracting process includes the following two phases:

 

Ø      Phase One:  The Contractor is selected and issued a Work Assignment for the Pre-Construction Phase. During this portion of the project, the contractor evaluates the work required, obtains quotes from applicable contractors, and develops the Guaranteed Maximum Price (GMP).

 

Ø      Phase Two:  The Eighth Amendment to the CMaR Contract No. 2023-17.001 is for the Construction Phase of the process.

 

The Department of Public Works provided a direct selection of Wharton-Smith, Inc., as the preferred CMaR to perform the repair services at the Family Services building. Accordingly, staff requests City Commission approval of the Eighth Amendment to CMaR Contract No. 2023-17.001 with Wharton-Smith, Inc., in the amount of $204,679.00.

 

The Eighth Amendment to Construction Manager at Risk Contract No. 2023-17.001 has been reviewed by the Interim City Attorney and is legally correct as to form.

 

Strategic Plan

 

Infrastructure & Facilities Integrity

Safe Community

 

Financial Impact

 

Funding in the amount of $204,679.00 is contingent upon adoption of Ordinance 2025-01 and will be allocated in the Fiscal Year 2025 budget in Project No. IAN22, account number 001-0760-519.46-04.

 

Procurement

 

Phase II - Repair Services at the Family Services Building Construction Manager at Risk Contract No. 2023-17.001 was procured pursuant Chapter 2 Administration, Article VIII Procurement, Section 2-406 Professional services selection under Consultants’ Competitive Negotiation Act (CCNA), F.S. § 287.055 of the Code of the City of North Port, Florida.

 

 

Attachments:

1.                     Contract Amendment No. 8

2.                     Contract

3.                     Florida Division of Corporations Document

 

 

 

Prepared by:                                            Garrett Woods, Senior Business Manager

 

Department Director:                       Chuck Speake, Public Works Director