TO: Honorable Mayor & Members of the North Port Commission
FROM: A. Jerome Fletcher II, ICMA-CM, MPA, City Manager
TITLE: Approve the Eighteenth Amendment to Construction Manager at Risk Contract No. 2023-17.001, Construction Services Contract Phase II, with Wharton-Smith, Inc., for Dallas White Park Boat Ramp Repair/Replacement at a Guaranteed Maximum Price of $699,854.00, for a Total Contract Amount of $750,315.40.
Recommended Action
Option 1: Approve the Eighteenth Amendment to Construction Manager at Risk Contract No. 2023-17.001, Construction Services Contract Phase II, with Wharton-Smith, Inc., for Dallas White Park boat ramp repair/replacement at a guaranteed maximum price of $699,854.00, for a total contract amount of $750,315.40
City Commission Options
Option 1: Approve the Eighteenth Amendment to Construction Manager at Risk Contract No. 2023-17.001, Construction Services Contract Phase II, with Wharton-Smith, Inc., for Dallas White Park boat ramp repair/replacement at a guaranteed maximum price of $699,854.00, for a total contract amount of $750,315.40.
• Pros: Authorizes replacement of damaged ramp components and shoreline erosion control to support public boating access.
• Cons: Commits funding in the amount of $699,854.00.
Option 2: Deny the Eighteenth Amendment to Construction Manager at Risk Contract No. 2023-17.001, Construction Services Contract Phase II, with Wharton-Smith, Inc., for Dallas White Park boat ramp repair/replacement at a guaranteed maximum price of $699,854.00, for a total contract amount of $750,315.40.
• Pros: Avoids the proposed construction commitment and allows reconsideration of scope and funding priorities.
• Cons: Delays ramp repair/replacement and shoreline stabilization while an alternative approach is developed.
Background Information
The boat ramp at Dallas White Park, was closed in 2024 as a result of damage from repeated impacts during major storms., is damaged, with a portion disengaged from the remaining concrete and extensive shoreline erosion. Phase II includes selective demolition, replacement ramp components and shoreline erosion control. Wharton-Smith, Inc., will coordinate permits, subcontractors, warranties and site cleanup.
On May 23, 2023, the City Commission approved multi-award continuing services contracts for Phase I CMAR preconstruction services, including Contract No. 2023-17.001 with Wharton-Smith, Inc Work assignments are issued as needed under the continuing contract.
The later project-specific Work Assignment No. 2025-53FM for Replacement Boat Ramp at Dallas White Park has a not-to-exceed preconstruction amount of $50,461.40, separate from the proposed construction GMP. Its scope includes assessment, engineering options, accessibility considerations, value engineering, estimates, scheduling and permitting, and bid/GMP preparation.
The CMAR process includes two phases. Phase I develops the scope, estimates and GMP. The Eighteenth Amendment would authorize Phase II construction based on the agreed GMP. [1.6] The Commission previously approved the Fourteenth Amendment on October 14, 2025, and the Sixteenth Amendment on January 20, 2026, for other Phase II work under this contract.
Wharton-Smith, Inc., submitted its November 3, 2026, proposal for the boat ramp project at a GMP of $699,854.00, consistent with Exhibit G.
City Attorney review and form determination: [City Attorney review]. City Clerk signature routing: [City Clerk routing]. Execution remains subject to City Commission approval.
Strategic Plan Pillar
Quality of Life
Financial Impact
Procurement
Attachments:
1. Default
Prepared by: FirstName LastName
Department Director: FirstName LastName