Title: Approve Change Order No. 1 to Work Assignment PW2022-01 for Continuing Contract No. 2016-32 Professional Surveying Services with Van Buskirk & Fish Surveying and Mapping, Inc., to Increase the Work Assignment Amount from $175,000 to an Estimated Amount of $228,600
Attachments: 1. Change Order, 2. Work Assignment, 3. Final Renewal Documents, 4. Contract, 5. Florida Division of Corporations Documents

TO:                                           Honorable Mayor & Members of the North Port Commission

 

FROM:                      A. Jerome Fletcher II, ICMA-CM, MPA, City Manager

 

TITLE:                     Approve Change Order No. 1 to Work Assignment PW2022-01 for Continuing Contract No. 2016-32 Professional Surveying Services with Van Buskirk & Fish Surveying and Mapping, Inc., to Increase the Work Assignment Amount from $175,000 to an Estimated Amount of $228,600

 

 

Recommended Action

 

Approve Change Order No. 1 to Work Assignment PW2022-01 for Continuing Contract No. 2016-32 Professional Surveying Services with Van Buskirk & Fish Surveying and Mapping, Inc., to increase the Work Assignment amount from $175,000 to an estimated amount of $228,600.

 

Background Information

 

The City of North Port advertised Request for Proposals (RFP) 2016-32 Professional Surveying Services to procure regular surveying services to be utilized by various City Departments. Commission approved Agreement 2016-32 on January 24, 2017, with the City Commission approving the final two-year renewal effective November 1, 2021, through October 31, 2023.

 

Commission approved WA No. PW2022-01 on September 28, 2021 for an estimated amount of $175,000.00 for miscellaneous small survey services and line and grade work.  The volume of work has increased and Public Works anticipates the need for an additional $53,600 in funds for the balance of the fiscal year.

 

Due to the continued increase of construction activity, staff recommends Commission approval of the following:

 

1.                     Increase the expenditures in Fiscal Year 2022 for Work Assignment PW2022-01 from $175,000 to an estimated amount of $228,600 based upon the current contracted hourly rates

 

Strategic Plan

 

Efficient and Effective Government

 

Financial Impact

 

Funding in the amount of $228,600 is available in the Fiscal Year 2022 budget, account number 107-5000-541.31-11.

 

Procurement

 

Continuing Contract No. 2016-32 was procured pursuant to Section 2-406 Professional Services Selection under Consultants’ Competitive Negotiation Act (CCNA), Florida Statutes § 287.055.

 

Vendor Information:

 

Van Buskirk & Fish Surveying and Mapping, Inc.

12450 Tamiami Trail, Unit D

North Port, Florida 34287

 

Attachments:

1.                     Change Order No. 1 to Work Assignment PW2022-01

2.                     Work Assignment No. PW2022-01

3.                     Final Renewal Documents

4.                     Contract No. 2016-32 Van Buskirk Fish & Associates Inc

5.   Florida Division of Corporations Document

 

 

 

Prepared by:                                            Garrett Woods, Business Manager

 

Department Director:                       Chuck Speake, Public Works Director