Title: Approve the Federally Funded Community Development Block Grant Mitigation Program Subrecipient Agreement in the Amount of $650,440 to be Used for Utilities Bypass Pump Project
Attachments: 1. Subrecipient Agreement, 2. Grant Application, 3. Resolution 2020-R-19

TO:                                           Honorable Mayor & Members of the North Port Commission

 

FROM:                      A. Jerome Fletcher, II, City Manager

 

TITLE:                     Approve Acceptance of the Federally Funded Community Development Block Grant Mitigation Program Subrecipient Agreement in the Amount of $650,440 to be Used for Utilities Bypass Pumps Project

 

 

Recommended Action

 

Approve acceptance of the Federally Funded Community Development Block Grant Mitigation Program Subrecipient Agreement in the amount of $650,440 to be used for Utilities Bypass Pumps Project.

 

Background Information

 

In June 2020, City staff applied to the Community Development Block Grant Disaster Relief Program (CDBG-DR) for the Utilities Inflow and Infiltration project.  The CDBG-DR program, administered in Florida by the Florida Department of Economic Opportunity (FDEO), provides housing, infrastructure, and economic revitalization assistance to disaster impacted low to moderate income areas. The project will improve the resiliency of the sanitary sewer system to the low to moderate income households by reducing sanitary sewer overflows during heavy rains by installing emergency bypass pumps on eight lift stations:

                     Lift Station 23 at 6142 Bolander Terrace

                     Lift Station 25 at 5810 Kenwood Drive

                     Lift Station 30 at 5033 Kingsley Road

                     Lift Station 37 at 7503 Mayland Street

                     Lift Station 38 at 7539 Wexford Street

                     Lift Station 39 at 14809 South Tamiami Trail

                     Lift Station 43 at 5725 Greenwood Avenue

                     Lift Station 63 at 4028 Fairway Drive

The cost of the project, which includes federal construction oversight, is expected to be $650,440. The project will be complete within four years.

In summer of 2021, FDEO staff contacted the City to inform us that the CDBG-DR grant would be transferred over to the Community Development Block Grant Mitigation Program (CDBG-MIT) to allow more flexibly with construction timelines. The CDBG-MIT program provides similar post disaster benefits to low to moderate income households. 

The grant contract has been reviewed for legal form and correctness.

Strategic Plan

 

Health & Public Safety

Infrastructure

 

Financial Impact

 

Funds will be budgeted under account number 420-6063-536.64-00. Matching funds are not required for this grant.

 

Procurement

 

Not applicable.

 

Attachments:

1.                     Federally Funded CDBG-MIT Subrecipient Agreement

2.                     Grant Application

3.                     Resolution 2020-R-19

 

 

Prepared by:                                            Valerie Malingowski, Grant Writer

 

Department Director:                       A. Jerome Fletcher, II, City Manager