File #: 19-0004    Version: 1 Name:
Type: General Business Status: Passed
File created: 1/3/2019 In control: Road and Drainage District Governing Body
On agenda: 1/22/2019 Final action: 1/22/2019
Title: Estimated Construction Cost - Price Boulevard Widening Project from Sumter Boulevard to Toledo Blade Boulevard.
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

TO:                                           Honorable Mayor & Members of the North Port Commission

 

FROM:                      Peter D. Lear, CPA, CGMA, City Manager

 

TITLE:                     Estimated Construction Cost - Price Boulevard Widening Project from Sumter Boulevard to Toledo Blade Boulevard

 

 

Recommended Action

 

No action required.

 

Background Information

 

During their Regular Meeting held on July 10, 2018, the City Commission requested an updated estimate of the construction costs of the Price Boulevard Widening Project from Sumter Boulevard to Toledo Blade Boulevard. The sixty percent (60%) complete Design Plans for the Project, including the Engineer’s Estimated Construction Cost were recently submitted for review by the Department of Public Works Engineering Division staff.

 

The following is the breakdown of the Engineer’s Estimated Construction Cost:

 

Roadway Construction                     $12,100,000

Stormwater Drainage                     $  4,530,000

Signalization                                          $     755,000

Roadway Lighting                     $  3,305,000

Utilities                                                               $  3,115,000

Mobilization                                          $  1,825,000

Maintenance of Traffic                     $  3,075,000

 

Total                                                                $28,705,000

 

 

The Engineer’s Estimated Construction Cost is based upon the acquisition of designated stormwater pond sites.  If these stormwater pond sites are not acquired, other vacant lots will be evaluated for suitability.  However, the number of vacant lots needed may increase and the amount of stormwater piping and structures necessary for transporting the stormwater to alternate stormwater pond sites will increase both in quantity and cost.  As the Project’s design is further developed, the construction cost estimate will be refined.

 

Other project costs include:

 

Design and Permitting                     $3,351,270

                     Land Acquisition                                                                                    $2,000,000

                     Construction Engineering and Inspection                     $4,310,000

 

                     Total                                                                                                                              $9,661,270

 

 

The current Capital Improvements Program allocates $40,347,320.00 for construction of the Price Boulevard Widening Project from Sumter Boulevard to Toledo Blade Boulevard.  The City’s Financial Consultant is working on funding options for the construction of this Project.

 

Strategic Plan

 

Infrastructure

 

Financial Impact

 

Not Applicable

 

Procurement

 

Not Applicable

 

 

Prepared by:                                            Benjamin Newman, P.E., Projects Engineer

 

Department Director:                       Juliana B. Bellia