TO: Honorable Mayor & Members of the North Port Commission
FROM: A. Jerome Fletcher II, ICMA-CM, MPA, City Manager
TITLE: Discussion and Possible Action Approve the Fifth Amendment to Construction Manager at Risk Contract No. 2023-17.002 for Construction Services Contract, Phase II With Halfacre Construction Company in the Amount of $54,447.05, for Hurricane Ian Repairs at LaBrea Park.
Recommended Action
Approve Fifth Amendment to Construction Manager at Risk Contract No. 2023-17.002 for Construction Services Contract, Phase II with Halfacre Construction Company in the amount of $54,447.05, for Hurricane Ian Repairs at LaBrea Park.
Background Information
As a result of impacts from Hurricane Ian, LaBrea Park suffered damage to chain link fencing, site signage, playground swing structures, shade canopy, and site trash receptacles, which is outlined in the Halliwell Construction Services and Rostan Damage Assessment Report.
In consultation with City Administration, the use of the Construction Manager at Risk (CMaR) Continuing Services Contract has been identified as the most expedient path to complete this project. The following describes the CMaR process specific to this project:
Ø December 27, 2023: Work Assignment No. 2024-06FM was issued to Halfacre Construction Company for pre-construction phase (Phase I) services. During this phase, the Contractor evaluated the work required, obtained quotes from applicable contractors, and developed the Guaranteed Maximum Price (GMP).
Ø May 21, 2024: Halfacre Construction Company submitted a GMP proposal. This Amendment to Contract No. 2023-17.002 presented for approval is for the construction phase (Phase II) of the process. The Project Manager with the Department of Public Works provided a direct selection of Halfacre Construction Company as the preferred CMaR to carry out the project at LaBrea Park and requests approval of this Amendment to proceed to construction.
The Fifth Amendment to Construction Manager at Risk Contract No. 2023-17.002 for Construction Services Contract, Phase II with Halfacre Construction Company for Hurricane Ian repairs at LaBrea Park has been reviewed by the City Attorney and is legally correct as to form. This item is contingent upon approval of the budget amendment appropriating funding.
Strategic Plan
Infrastructure & Facilities Integrity
Financial Impact
Funding in the amount of $54,447.05 is contingent upon adoption of Ordinance 2024-36 and will be allocated in the Parks & Recreation Department Fiscal Year 2024 budget in Project No. IAN22, account number 001-3038-572-46-03.
Procurement
Contract No. 2023-17.002 was procured pursuant to Sec. 2-406 Professional Services selection under the Consultants Competitive Negotiation Act (CCNA), F.S. § 287.055 of the Code of the City of North Port, Florida.
CMAR Process:
Ø Phase I: The Contractor is selected and issued a Work Assignment for the pre-construction phase.
Ø Phase II: The GMP for the construction phase was negotiated for Hurricane Ian repairs at LaBrea Park.
Attachments:
1. Fifth Amendment to Contract No. 2023-17.002
2. Contract No. 2023-17.002
3. Work Assignment 2024-06FM
4. Florida Division of Corporations Document
Prepared by: Cheryl Greiner, Business Operations Manager
Department Director: Sandy Pfundheller, Parks & Recreation Director