TO: Honorable Mayor & Members of the North Port Commission
FROM: A. Jerome Fletcher II, ICMA-CM, MPA, City Manager
TITLE: Approve Utilization of Contract R220402 Between Region 4 Education Service Center and SAK Construction, LLC for Trenchless Technology Rehabilitation and Related Products and Services in an Amount not to Exceed $2,000,000 Annually Through the Term Ending February 28, 2027, and Authorize the City Manager to Approve any Modifications, Terminations or Renewals in Concurrence with Region 4 Education Service Center.
Recommended Action
Option 1: Approve utilization of Contract R220402 between Region 4 Education Service Center and SAK Construction, LLC for trenchless technology rehabilitation and related products and services in an amount not to exceed $2,000,000 annually through the term ending February 28, 2027, and authorize the City Manager to approve any modifications, terminations, or renewals in concurrence with Region 4 Education Service Center.
City Commission Options
Option 1: Approve utilization of Contract R220402 between Region 4 Education Service Center and SAK Construction, LLC for trenchless technology rehabilitation and related products and services in an amount not to exceed $2,000,000 annually through the term ending February 28, 2027, and authorize the City Manager to approve any modifications, terminations, or renewals in concurrence with Region 4 Education Service Center.
Pros: Provides timely access to competitively procured trenchless rehabilitation services at established contract pricing without conducting a separate City solicitation.
Cons: Authorizes expenditures of up to $2,000,000 annually, which reduces funding available for other infrastructure priorities as funds are utilized.
Option 2: Deny the use of Contract R220402 between Region 4 Education Service Center and SAK Construction, LLC.
Pros: Staff have not identified any foreseeable benefits associated with denying utilization of the contract.
Cons: May del...